Orise construction photos
21 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Orise was built on the day of each visit.
7 May 20268.6% built
28 January 20266.0% built
24 October 20254.2% built
22 July 20251.0% built
14 April 20250% built
25 November 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.