Wadi Hills By Hre construction progress

Wadi Hills By Hre in Dubai Land Residence Complex is 7.7% built at the Land Department inspection of September 2026. Developer Wadi Hills City Real Estate Development. Completion registered for January 2028.

7.7%

Built, at the Land Department site inspection of 14 September 2026

Running behind its date

Completion date (Land Department)
January 2028
Finish at recent pace
May 2038
Construction started
November 2025
Registered with the Land Department
September 2025
Developer
Wadi Hills City Real Estate Development
Units
131
Escrow bank
Sharjah Islamic Bank
Name in Arabic
وادي هيلز من اتش ار اي
Land Department project number
4100
Land Department site inspections
4

Schedule

Between September 2025 and September 2026 the site added about 0.7 points a month. At that rate it would finish around May 2038, more than three months after the January 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 September 2026

7.7%+5.1 pts

  • Wadi Hills By Hre construction site, Land Department inspection photo 1, 14 September 2026
  • Wadi Hills By Hre construction site, Land Department inspection photo 2, 14 September 2026
  • Wadi Hills By Hre construction site, Land Department inspection photo 3, 14 September 2026
  • Wadi Hills By Hre construction site, Land Department inspection photo 4, 14 September 2026

4 June 2026

2.6%+2.6 pts

  • Wadi Hills By Hre construction site, Land Department inspection photo 1, 4 June 2026
  • Wadi Hills By Hre construction site, Land Department inspection photo 2, 4 June 2026
  • Wadi Hills By Hre construction site, Land Department inspection photo 3, 4 June 2026
  • Wadi Hills By Hre construction site, Land Department inspection photo 4, 4 June 2026

24 February 2026

0%+0.0 pts

  • Wadi Hills By Hre construction site, Land Department inspection photo 1, 24 February 2026
  • Wadi Hills By Hre construction site, Land Department inspection photo 2, 24 February 2026
  • Wadi Hills By Hre construction site, Land Department inspection photo 3, 24 February 2026
  • Wadi Hills By Hre construction site, Land Department inspection photo 4, 24 February 2026

22 September 2025

0%

  • Wadi Hills By Hre construction site, Land Department inspection photo 1, 22 September 2025
  • Wadi Hills By Hre construction site, Land Department inspection photo 2, 22 September 2025

All 14 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Own a unit in Wadi Hills By Hre?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Wadi Hills By Hre be completed?
The completion date registered with the Dubai Land Department is January 2028. At the pace of its recent inspections the site would reach 100% around May 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Wadi Hills By Hre is built?
7.7%, measured at the Land Department site inspection on 14 September 2026. The Land Department engineers have inspected the site 4 times since September 2025.
Is Wadi Hills By Hre delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2028.
Who is building Wadi Hills By Hre?
The registered developer is Wadi Hills City Real Estate Development.
Which bank holds the escrow account for Wadi Hills By Hre?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.