Solanki One construction progress
The registered completion date for Solanki One in Dubai Land Residence Complex is May 2028. At the last site inspection, in September 2026, it was 35% built. The developer is Solanki Real Estate Development.
35%
Built, at the site inspection of 14 September 2026
On pace for its date
- Registered completion date
- May 2028
- Finish at recent pace
- June 2028
- Construction started
- May 2025
- First registered
- August 2025
- Developer
- Solanki Real Estate Development
- Community
- Dubai Land Residence Complex
- Units
- 133
- Escrow bank
- Emirates NBD
- Name in Arabic
- سولانكي ون
- Project number
- 3776
- Site inspections
- 4
Schedule
Since February 2026 Solanki One has added about 3.1 points a month. That puts 100% around June 2028, within three months of its registered completion date of May 2028.
Site inspections
14 September 2026
35%+13 pts
19 May 2026
22%+9.4 pts
5 February 2026
12%+9.8 pts
25 July 2025
2.5%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Own a unit in Solanki One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Solanki One handover date?
- The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Solanki One?
- Solanki One was 35% built at the site inspection on 14 September 2026. The site has been inspected 4 times since July 2025. The Land Department took 22 site photos at its inspections.
- Is Solanki One delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2028.
- Who is building Solanki One?
- The registered developer is Solanki Real Estate Development.
- Which bank holds the escrow account for Solanki One?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.











