Solanki One construction progress

The registered completion date for Solanki One in Dubai Land Residence Complex is May 2028. At the last site inspection, in September 2026, it was 35% built. The developer is Solanki Real Estate Development.

35%

Built, at the site inspection of 14 September 2026

On pace for its date

Registered completion date
May 2028
Finish at recent pace
June 2028
Construction started
May 2025
First registered
August 2025
Developer
Solanki Real Estate Development
Units
133
Escrow bank
Emirates NBD
Name in Arabic
سولانكي ون
Project number
3776
Site inspections
4

Schedule

Since February 2026 Solanki One has added about 3.1 points a month. That puts 100% around June 2028, within three months of its registered completion date of May 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 September 2026

35%+13 pts

  • Solanki One construction site, inspection photo 1, 14 September 2026
  • Solanki One construction site, inspection photo 2, 14 September 2026
  • Solanki One construction site, inspection photo 3, 14 September 2026
  • Solanki One construction site, inspection photo 4, 14 September 2026

19 May 2026

22%+9.4 pts

  • Solanki One construction site, inspection photo 1, 19 May 2026
  • Solanki One construction site, inspection photo 2, 19 May 2026
  • Solanki One construction site, inspection photo 3, 19 May 2026
  • Solanki One construction site, inspection photo 4, 19 May 2026

5 February 2026

12%+9.8 pts

  • Solanki One construction site, inspection photo 1, 5 February 2026
  • Solanki One construction site, inspection photo 2, 5 February 2026
  • Solanki One construction site, inspection photo 3, 5 February 2026
  • Solanki One construction site, inspection photo 4, 5 February 2026

25 July 2025

2.5%

  • Solanki One construction site, inspection photo 1, 25 July 2025
  • Solanki One construction site, inspection photo 2, 25 July 2025
  • Solanki One construction site, inspection photo 3, 25 July 2025
  • Solanki One construction site, inspection photo 4, 25 July 2025

All 22 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Own a unit in Solanki One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Solanki One handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Solanki One?
Solanki One was 35% built at the site inspection on 14 September 2026. The site has been inspected 4 times since July 2025. The Land Department took 22 site photos at its inspections.
Is Solanki One delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2028.
Who is building Solanki One?
The registered developer is Solanki Real Estate Development.
Which bank holds the escrow account for Solanki One?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.