Shorooq Land 1 construction progress

The register lists Shorooq Land 1 in Dubai Land Residence Complex as complete, with a registered completion date of January 2022. Its last site inspection on record was in January 2022. The developer is Wishes Land Real Estate Development.

100%

Built, at the site inspection of 4 January 2022

Construction complete

Registered completion date
January 2022
Construction started
April 2017
First registered
December 2017
Developer
Wishes Land Real Estate Development
Units
244
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
شروق لاند 1
Project number
2008
Site inspections
3

Schedule

The register lists Shorooq Land 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20182019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 January 2022

100%+72 pts

  • Shorooq Land 1 construction site, inspection photo 1, 4 January 2022
  • Shorooq Land 1 construction site, inspection photo 2, 4 January 2022
  • Shorooq Land 1 construction site, inspection photo 3, 4 January 2022
  • Shorooq Land 1 construction site, inspection photo 4, 4 January 2022

30 July 2018

28%+7.4 pts

  • Shorooq Land 1 construction site, inspection photo 1, 30 July 2018
  • Shorooq Land 1 construction site, inspection photo 2, 30 July 2018
  • Shorooq Land 1 construction site, inspection photo 3, 30 July 2018
  • Shorooq Land 1 construction site, inspection photo 4, 30 July 2018

25 April 2018

20%

  • Shorooq Land 1 construction site, inspection photo 1, 25 April 2018
  • Shorooq Land 1 construction site, inspection photo 2, 25 April 2018
  • Shorooq Land 1 construction site, inspection photo 3, 25 April 2018
  • Shorooq Land 1 construction site, inspection photo 4, 25 April 2018

All 28 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Own a unit in Shorooq Land 1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Shorooq Land 1 handover date?
Construction of Shorooq Land 1 is recorded as complete, with a registered completion date of January 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Shorooq Land 1?
Shorooq Land 1 was 100% built at the site inspection on 4 January 2022. The site has been inspected 3 times since April 2018. The Land Department took 28 site photos at its inspections.
Is Shorooq Land 1 delayed?
The register lists construction as complete.
Who is building Shorooq Land 1?
The registered developer is Wishes Land Real Estate Development.
Which bank holds the escrow account for Shorooq Land 1?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.