Saray Prime Residence construction progress

The registered completion date for Saray Prime Residence in Dubai Land Residence Complex is October 2027. At the last site inspection, in September 2026, it was 2.2% built. The developer is Unique Saray Properties.

2.2%

Built, at the site inspection of 21 September 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
April 2065
Construction started
November 2025
First registered
November 2025
Developer
Unique Saray Properties
Units
121
Escrow bank
Emirates NBD
Name in Arabic
سراي برايم ريزيدنس
Project number
4058
Site inspections
3

Schedule

Between November 2025 and September 2026 the site added about 0.2 points a month. At that rate it would finish around April 2065, more than three months after its registered date of October 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 September 2026

2.2%+0.5 pts

  • Saray Prime Residence construction site, inspection photo 1, 21 September 2026
  • Saray Prime Residence construction site, inspection photo 2, 21 September 2026
  • Saray Prime Residence construction site, inspection photo 3, 21 September 2026
  • Saray Prime Residence construction site, inspection photo 4, 21 September 2026

11 June 2026

1.7%+1.7 pts

  • Saray Prime Residence construction site, inspection photo 1, 11 June 2026
  • Saray Prime Residence construction site, inspection photo 2, 11 June 2026
  • Saray Prime Residence construction site, inspection photo 3, 11 June 2026

5 November 2025

0%

  • Saray Prime Residence construction site, inspection photo 1, 5 November 2025
  • Saray Prime Residence construction site, inspection photo 2, 5 November 2025
  • Saray Prime Residence construction site, inspection photo 3, 5 November 2025

All 10 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Own a unit in Saray Prime Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Saray Prime Residence handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2065. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Saray Prime Residence?
Saray Prime Residence was 2.2% built at the site inspection on 21 September 2026. The site has been inspected 3 times since November 2025. The Land Department took 10 site photos at its inspections.
Is Saray Prime Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Saray Prime Residence?
The registered developer is Unique Saray Properties.
Which bank holds the escrow account for Saray Prime Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.