Roof Comfort construction progress
Roof Comfort in Dubai Land Residence Complex is 50% built at the Land Department inspection of July 2026. Developer Roof Enterprises And Development Co. Completion registered for December 2027.
50%
Built, at the Land Department site inspection of 28 July 2026
On pace for its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- October 2027
- Construction started
- April 2025
- Registered with the Land Department
- June 2025
- Developer
- Roof Enterprises And Development Co
- Community
- Dubai Land Residence Complex
- Units
- 316
- Escrow bank
- Emirates NBD
- Name in Arabic
- روف كمفورت
- Land Department project number
- 3629
- Land Department site inspections
- 2
Schedule
Since May 2025 Roof Comfort has added about 3.5 points a month. That puts 100% around October 2027, within three months of its registered completion date of December 2027.
Site inspections
28 July 2026
50%+50 pts
14 May 2025
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average. Roof Comfort is ahead of that average.
Own a unit in Roof Comfort?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Roof Comfort be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Roof Comfort is built?
- 50%, measured at the Land Department site inspection on 28 July 2026. The Land Department engineers have inspected the site 2 times since May 2025.
- Is Roof Comfort delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2027.
- Who is building Roof Comfort?
- The registered developer is Roof Enterprises And Development Co.
- Which bank holds the escrow account for Roof Comfort?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.