Lateral One construction progress
The registered completion date for Lateral One in Dubai Land Residence Complex is December 2026. At the last site inspection, in October 2026, it was 79% built. The developer is Grand Signature Real Estate Development.
79%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- June 2027
- Construction started
- January 2025
- First registered
- December 2025
- Developer
- Grand Signature Real Estate Development
- Community
- Dubai Land Residence Complex
- Units
- 40
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- ليتيرال ون
- Project number
- 4086
- Site inspections
- 3
Schedule
Between November 2025 and October 2026 the site added about 2.9 points a month. At that rate it would finish around June 2027, more than three months after its registered date of December 2026.
Site inspections
28 October 2026
79%+6.8 pts
19 May 2026
72%+25 pts
24 November 2025
47%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Own a unit in Lateral One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lateral One handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lateral One?
- Lateral One was 79% built at the site inspection on 28 October 2026. The site has been inspected 3 times since November 2025. The Land Department took 22 site photos at its inspections.
- Is Lateral One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Lateral One?
- The registered developer is Grand Signature Real Estate Development.
- Which bank holds the escrow account for Lateral One?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.