Lateral One construction progress

The registered completion date for Lateral One in Dubai Land Residence Complex is December 2026. At the last site inspection, in October 2026, it was 79% built. The developer is Grand Signature Real Estate Development.

79%

Built, at the site inspection of 28 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
June 2027
Construction started
January 2025
First registered
December 2025
Developer
Grand Signature Real Estate Development
Units
40
Escrow bank
The National Bank of Fujairah
Name in Arabic
ليتيرال ون
Project number
4086
Site inspections
3

Schedule

Between November 2025 and October 2026 the site added about 2.9 points a month. At that rate it would finish around June 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

79%+6.8 pts

  • Lateral One construction site, inspection photo 1, 28 October 2026
  • Lateral One construction site, inspection photo 2, 28 October 2026
  • Lateral One construction site, inspection photo 3, 28 October 2026
  • Lateral One construction site, inspection photo 4, 28 October 2026

19 May 2026

72%+25 pts

  • Lateral One construction site, inspection photo 1, 19 May 2026
  • Lateral One construction site, inspection photo 2, 19 May 2026
  • Lateral One construction site, inspection photo 3, 19 May 2026
  • Lateral One construction site, inspection photo 4, 19 May 2026

24 November 2025

47%

  • Lateral One construction site, inspection photo 1, 24 November 2025
  • Lateral One construction site, inspection photo 2, 24 November 2025
  • Lateral One construction site, inspection photo 3, 24 November 2025
  • Lateral One construction site, inspection photo 4, 24 November 2025

All 22 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Own a unit in Lateral One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lateral One handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lateral One?
Lateral One was 79% built at the site inspection on 28 October 2026. The site has been inspected 3 times since November 2025. The Land Department took 22 site photos at its inspections.
Is Lateral One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Lateral One?
The registered developer is Grand Signature Real Estate Development.
Which bank holds the escrow account for Lateral One?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.