Skip to content

Dalmore Tower construction progress

Dalmore Tower in Dubai Land Residence Complex was registered to complete in April 2026 and is still under construction. At the last site inspection, in October 2026, it was 95% built. The developer is Dalmore Real Estate Development.

95%

Built, at the site inspection of 5 October 2026

7 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
November 2026
Construction started
October 2024
First registered
May 2025
Developer
Dalmore Real Estate Development
Units
120
Escrow bank
Mashreq Bank
Name in Arabic
برج دالمور
Project number
3622
Site inspections
5

Schedule

Dalmore Tower was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around November 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 October 2026

95%+8.3 pts

  • Dalmore Tower construction site, inspection photo 1, 5 October 2026
  • Dalmore Tower construction site, inspection photo 2, 5 October 2026
  • Dalmore Tower construction site, inspection photo 3, 5 October 2026
  • Dalmore Tower construction site, inspection photo 4, 5 October 2026

19 May 2026

87%+28 pts

  • Dalmore Tower construction site, inspection photo 1, 19 May 2026
  • Dalmore Tower construction site, inspection photo 2, 19 May 2026
  • Dalmore Tower construction site, inspection photo 3, 19 May 2026
  • Dalmore Tower construction site, inspection photo 4, 19 May 2026

28 October 2025

59%+28 pts

  • Dalmore Tower construction site, inspection photo 1, 28 October 2025
  • Dalmore Tower construction site, inspection photo 2, 28 October 2025
  • Dalmore Tower construction site, inspection photo 3, 28 October 2025
  • Dalmore Tower construction site, inspection photo 4, 28 October 2025

18 June 2025

31%+11 pts

  • Dalmore Tower construction site, inspection photo 1, 18 June 2025
  • Dalmore Tower construction site, inspection photo 2, 18 June 2025
  • Dalmore Tower construction site, inspection photo 3, 18 June 2025
  • Dalmore Tower construction site, inspection photo 4, 18 June 2025

14 April 2025

21%

  • Dalmore Tower construction site, inspection photo 1, 14 April 2025
  • Dalmore Tower construction site, inspection photo 2, 14 April 2025
  • Dalmore Tower construction site, inspection photo 3, 14 April 2025
  • Dalmore Tower construction site, inspection photo 4, 14 April 2025

All 42 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Own a unit in Dalmore Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Dalmore Tower handover date?
The registered completion date was April 2026, and the register still lists Dalmore Tower as under construction. At the pace of its recent inspections the site would reach 100% around November 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Dalmore Tower?
Dalmore Tower was 95% built at the site inspection on 5 October 2026. The site has been inspected 5 times since April 2025. The Land Department took 42 site photos at its inspections.
Is Dalmore Tower delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Dalmore Tower?
The registered developer is Dalmore Real Estate Development.
Which bank holds the escrow account for Dalmore Tower?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.