Bliss Tower construction progress

Bliss Tower in Dubai Land Residence Complex is 93% built at the Land Department inspection of September 2026. Developer Pure Bliss Development. Completion registered for December 2026.

93%

Built, at the Land Department site inspection of 17 September 2026

On pace for its date

Completion date (Land Department)
December 2026
Finish at recent pace
November 2026
Construction started
August 2024
Registered with the Land Department
June 2025
Developer
Pure Bliss Development
Units
131
Escrow bank
The National Bank of Fujairah
Name in Arabic
برج بليس
Land Department project number
3545
Land Department site inspections
5

Schedule

Since October 2025 Bliss Tower has added about 5.1 points a month. That puts 100% around November 2026, within three months of its registered completion date of December 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 September 2026

93%+28 pts

  • Bliss Tower construction site, Land Department inspection photo 1, 17 September 2026
  • Bliss Tower construction site, Land Department inspection photo 2, 17 September 2026
  • Bliss Tower construction site, Land Department inspection photo 3, 17 September 2026
  • Bliss Tower construction site, Land Department inspection photo 4, 17 September 2026

19 May 2026

65%+13 pts

  • Bliss Tower construction site, Land Department inspection photo 1, 19 May 2026
  • Bliss Tower construction site, Land Department inspection photo 2, 19 May 2026
  • Bliss Tower construction site, Land Department inspection photo 3, 19 May 2026
  • Bliss Tower construction site, Land Department inspection photo 4, 19 May 2026

29 January 2026

51%+14 pts

  • Bliss Tower construction site, Land Department inspection photo 1, 29 January 2026
  • Bliss Tower construction site, Land Department inspection photo 2, 29 January 2026
  • Bliss Tower construction site, Land Department inspection photo 3, 29 January 2026
  • Bliss Tower construction site, Land Department inspection photo 4, 29 January 2026

20 October 2025

37%+17 pts

  • Bliss Tower construction site, Land Department inspection photo 1, 20 October 2025
  • Bliss Tower construction site, Land Department inspection photo 2, 20 October 2025
  • Bliss Tower construction site, Land Department inspection photo 3, 20 October 2025
  • Bliss Tower construction site, Land Department inspection photo 4, 20 October 2025

4 April 2025

20%

  • Bliss Tower construction site, Land Department inspection photo 1, 4 April 2025
  • Bliss Tower construction site, Land Department inspection photo 2, 4 April 2025
  • Bliss Tower construction site, Land Department inspection photo 3, 4 April 2025
  • Bliss Tower construction site, Land Department inspection photo 4, 4 April 2025

All 44 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Own a unit in Bliss Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Bliss Tower be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Bliss Tower is built?
93%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 5 times since April 2025.
Is Bliss Tower delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building Bliss Tower?
The registered developer is Pure Bliss Development.
Which bank holds the escrow account for Bliss Tower?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.