Al Waleed W.s 1 construction progress

Al Waleed W.s 1 in Dubai Land Residence Complex is 18% built at the Land Department inspection of June 2026. Developer Al Waleed Development. Completion registered for February 2027.

18%

Built, at the Land Department site inspection of 18 June 2026

Running behind its date

Completion date (Land Department)
February 2027
Finish at recent pace
July 2031
Construction started
May 2025
Registered with the Land Department
July 2025
Developer
Al Waleed Development
Units
151
Escrow bank
Emirates NBD
Name in Arabic
الوليد دبليو.اس 1
Land Department project number
3712
Land Department site inspections
2

Schedule

Between May 2025 and June 2026 the site added about 1.3 points a month. At that rate it would finish around July 2031, more than three months after the February 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

18%+18 pts

  • Al Waleed W.s 1 construction site, Land Department inspection photo 1, 18 June 2026
  • Al Waleed W.s 1 construction site, Land Department inspection photo 2, 18 June 2026
  • Al Waleed W.s 1 construction site, Land Department inspection photo 3, 18 June 2026
  • Al Waleed W.s 1 construction site, Land Department inspection photo 4, 18 June 2026

1 May 2025

0%

  • Al Waleed W.s 1 construction site, Land Department inspection photo 1, 1 May 2025
  • Al Waleed W.s 1 construction site, Land Department inspection photo 2, 1 May 2025

All 7 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average. Al Waleed W.s 1 is behind that average.

Own a unit in Al Waleed W.s 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Al Waleed W.s 1 be completed?
The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around July 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Al Waleed W.s 1 is built?
18%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 2 times since May 2025.
Is Al Waleed W.s 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Al Waleed W.s 1?
The registered developer is Al Waleed Development.
Which bank holds the escrow account for Al Waleed W.s 1?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.