Ajmal Sarah construction progress

The register lists Ajmal Sarah in Dubai Land Residence Complex as complete, with a registered completion date of October 2015. Its last site inspection on record was in October 2015. The developer is Fabson Import Export Limited.

100%

Built, at the site inspection of 6 October 2015

Construction complete

Registered completion date
October 2015
Construction started
April 2008
First registered
November 2008
Developer
Fabson Import Export Limited
Units
302
Escrow bank
Dubai Islamic Bank
Name in Arabic
أجمل سارة
Project number
394
Site inspections
4

Schedule

The register lists Ajmal Sarah as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2009201120132015
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 October 2015

100%+8.5 pts

  • Ajmal Sarah construction site, inspection photo 1, 6 October 2015
  • Ajmal Sarah construction site, inspection photo 2, 6 October 2015

10 July 2014

91%+15 pts

  • Ajmal Sarah construction site, inspection photo 1, 10 July 2014
  • Ajmal Sarah construction site, inspection photo 2, 10 July 2014
  • Ajmal Sarah construction site, inspection photo 3, 10 July 2014
  • Ajmal Sarah construction site, inspection photo 4, 10 July 2014

1 February 2014

77%+9.1 pts

  • Ajmal Sarah construction site, inspection photo 1, 1 February 2014
  • Ajmal Sarah construction site, inspection photo 2, 1 February 2014
  • Ajmal Sarah construction site, inspection photo 3, 1 February 2014
  • Ajmal Sarah construction site, inspection photo 4, 1 February 2014

12 June 2013

67%

  • Ajmal Sarah construction site, inspection photo 1, 12 June 2013
  • Ajmal Sarah construction site, inspection photo 2, 12 June 2013
  • Ajmal Sarah construction site, inspection photo 3, 12 June 2013
  • Ajmal Sarah construction site, inspection photo 4, 12 June 2013

All 37 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Own a unit in Ajmal Sarah?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Ajmal Sarah handover date?
Construction of Ajmal Sarah is recorded as complete, with a registered completion date of October 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Ajmal Sarah?
Ajmal Sarah was 100% built at the site inspection on 6 October 2015. The site has been inspected 4 times since June 2013. The Land Department took 37 site photos at its inspections.
Is Ajmal Sarah delayed?
The register lists construction as complete.
Who is building Ajmal Sarah?
The registered developer is Fabson Import Export Limited.
Which bank holds the escrow account for Ajmal Sarah?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.