Ag Aum Residence construction progress

The registered completion date for Ag Aum Residence in Dubai Land Residence Complex is November 2028. At the last site inspection, in October 2026, it was 8.1% built. The developer is Agp Assets Real Estate Developments.

8.1%

Built, at the site inspection of 28 October 2026

Running behind its date

Registered completion date
November 2028
Finish at recent pace
July 2036
Construction started
November 2024
First registered
October 2024
Developer
Agp Assets Real Estate Developments
Units
260
Escrow bank
Emirates NBD
Name in Arabic
ايه جي أوم السكني
Project number
3262
Site inspections
4

Schedule

Between March 2026 and October 2026 the site added about 0.8 points a month. At that rate it would finish around July 2036, more than three months after its registered date of November 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

8.1%+5.6 pts

  • Ag Aum Residence construction site, inspection photo 1, 28 October 2026
  • Ag Aum Residence construction site, inspection photo 2, 28 October 2026
  • Ag Aum Residence construction site, inspection photo 3, 28 October 2026
  • Ag Aum Residence construction site, inspection photo 4, 28 October 2026

24 March 2026

2.4%+2.0 pts

  • Ag Aum Residence construction site, inspection photo 1, 24 March 2026
  • Ag Aum Residence construction site, inspection photo 2, 24 March 2026
  • Ag Aum Residence construction site, inspection photo 3, 24 March 2026

21 July 2025

0.4%+0.4 pts

  • Ag Aum Residence construction site, inspection photo 1, 21 July 2025
  • Ag Aum Residence construction site, inspection photo 2, 21 July 2025
  • Ag Aum Residence construction site, inspection photo 3, 21 July 2025
  • Ag Aum Residence construction site, inspection photo 4, 21 July 2025

12 September 2024

0%

  • Ag Aum Residence construction site, inspection photo 1, 12 September 2024
  • Ag Aum Residence construction site, inspection photo 2, 12 September 2024

All 15 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Own a unit in Ag Aum Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ag Aum Residence handover date?
The registered completion date is November 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ag Aum Residence?
Ag Aum Residence was 8.1% built at the site inspection on 28 October 2026. The site has been inspected 4 times since September 2024. The Land Department took 15 site photos at its inspections.
Is Ag Aum Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2028.
Who is building Ag Aum Residence?
The registered developer is Agp Assets Real Estate Developments.
Which bank holds the escrow account for Ag Aum Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.