Ag Ark Tower construction progress

The registered completion date for Ag Ark Tower in Dubai Land Residence Complex is November 2028. At the last site inspection, in October 2026, it was 14% built. The developer is Agp Ark Real Estate Development.

14%

Built, at the site inspection of 28 October 2026

Running behind its date

Registered completion date
November 2028
Finish at recent pace
September 2031
Construction started
November 2024
First registered
October 2024
Developer
Agp Ark Real Estate Development
Units
189
Escrow bank
Emirates NBD
Name in Arabic
برج ايه جي أرك
Project number
3313
Site inspections
4

Schedule

Between March 2026 and October 2026 the site added about 1.5 points a month. At that rate it would finish around September 2031, more than three months after its registered date of November 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

14%+11 pts

  • Ag Ark Tower construction site, inspection photo 1, 28 October 2026
  • Ag Ark Tower construction site, inspection photo 2, 28 October 2026
  • Ag Ark Tower construction site, inspection photo 3, 28 October 2026
  • Ag Ark Tower construction site, inspection photo 4, 28 October 2026

18 March 2026

3.2%+1.7 pts

  • Ag Ark Tower construction site, inspection photo 1, 18 March 2026
  • Ag Ark Tower construction site, inspection photo 2, 18 March 2026
  • Ag Ark Tower construction site, inspection photo 3, 18 March 2026

4 August 2025

1.5%+1.5 pts

  • Ag Ark Tower construction site, inspection photo 1, 4 August 2025
  • Ag Ark Tower construction site, inspection photo 2, 4 August 2025
  • Ag Ark Tower construction site, inspection photo 3, 4 August 2025
  • Ag Ark Tower construction site, inspection photo 4, 4 August 2025

1 October 2024

0%

  • Ag Ark Tower construction site, inspection photo 1, 1 October 2024
  • Ag Ark Tower construction site, inspection photo 2, 1 October 2024

All 14 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Own a unit in Ag Ark Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ag Ark Tower handover date?
The registered completion date is November 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ag Ark Tower?
Ag Ark Tower was 14% built at the site inspection on 28 October 2026. The site has been inspected 4 times since October 2024. The Land Department took 14 site photos at its inspections.
Is Ag Ark Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2028.
Who is building Ag Ark Tower?
The registered developer is Agp Ark Real Estate Development.
Which bank holds the escrow account for Ag Ark Tower?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.