Maple construction progress

The register lists Maple in Dubai Hills as complete, with a registered completion date of September 2019. Its last site inspection on record was in September 2019. The developer is Dubai Hills Estate.

100%

Built, at the site inspection of 10 September 2019

Construction complete

Registered completion date
September 2019
Construction started
December 2016
First registered
April 2015
Community
Dubai Hills
Units
646
Escrow bank
Dubai Islamic Bank
Name in Arabic
مابل
Project number
1645
Site inspections
13

Schedule

The register lists Maple as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2016201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 September 2019

100%+3.8 pts

  • Maple construction site, inspection photo 1, 10 September 2019
  • Maple construction site, inspection photo 2, 10 September 2019
  • Maple construction site, inspection photo 3, 10 September 2019
  • Maple construction site, inspection photo 4, 10 September 2019

16 May 2019

96%+5.9 pts

  • Maple construction site, inspection photo 1, 16 May 2019
  • Maple construction site, inspection photo 2, 16 May 2019
  • Maple construction site, inspection photo 3, 16 May 2019
  • Maple construction site, inspection photo 4, 16 May 2019

3 February 2019

90%+10 pts

  • Maple construction site, inspection photo 1, 3 February 2019
  • Maple construction site, inspection photo 2, 3 February 2019
  • Maple construction site, inspection photo 3, 3 February 2019
  • Maple construction site, inspection photo 4, 3 February 2019

1 November 2018

80%+5.0 pts

  • Maple construction site, inspection photo 1, 1 November 2018
  • Maple construction site, inspection photo 2, 1 November 2018
  • Maple construction site, inspection photo 3, 1 November 2018
  • Maple construction site, inspection photo 4, 1 November 2018

11 September 2018

75%+7.4 pts

  • Maple construction site, inspection photo 1, 11 September 2018
  • Maple construction site, inspection photo 2, 11 September 2018
  • Maple construction site, inspection photo 3, 11 September 2018
  • Maple construction site, inspection photo 4, 11 September 2018

24 May 2018

68%+2.4 pts

  • Maple construction site, inspection photo 1, 24 May 2018
  • Maple construction site, inspection photo 2, 24 May 2018
  • Maple construction site, inspection photo 3, 24 May 2018
  • Maple construction site, inspection photo 4, 24 May 2018

16 April 2018

65%+14 pts

  • Maple construction site, inspection photo 1, 16 April 2018
  • Maple construction site, inspection photo 2, 16 April 2018
  • Maple construction site, inspection photo 3, 16 April 2018
  • Maple construction site, inspection photo 4, 16 April 2018

18 January 2018

52%+27 pts

  • Maple construction site, inspection photo 1, 18 January 2018
  • Maple construction site, inspection photo 2, 18 January 2018
  • Maple construction site, inspection photo 3, 18 January 2018
  • Maple construction site, inspection photo 4, 18 January 2018

6 September 2017

25%+12 pts

  • Maple construction site, inspection photo 1, 6 September 2017
  • Maple construction site, inspection photo 2, 6 September 2017
  • Maple construction site, inspection photo 3, 6 September 2017
  • Maple construction site, inspection photo 4, 6 September 2017

10 May 2017

12%+2.0 pts

  • Maple construction site, inspection photo 1, 10 May 2017
  • Maple construction site, inspection photo 2, 10 May 2017
  • Maple construction site, inspection photo 3, 10 May 2017
  • Maple construction site, inspection photo 4, 10 May 2017

All 119 site photos, by inspection date

Context

Dubai Hills has 2 projects under construction, 73% built on average.

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Maple?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Maple handover date?
Construction of Maple is recorded as complete, with a registered completion date of September 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Maple?
Maple was 100% built at the site inspection on 10 September 2019. The site has been inspected 13 times since October 2015. The Land Department took 119 site photos at its inspections.
Is Maple delayed?
The register lists construction as complete.
Who is building Maple?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Maple?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.