Skip to content

Sidra 2 construction progress

The register lists Sidra 2 in Dubai Hills - Sidra 2 as complete, with a registered completion date of June 2019. Its last site inspection on record was in February 2020. The developer is Dubai Hills Estate.

100%

Built, at the site inspection of 13 February 2020

Construction complete

Registered completion date
June 2019
Construction started
May 2017
First registered
December 2016
Community
Dubai Hills - Sidra 2
Units
422
Escrow bank
Emirates NBD
Name in Arabic
سدره 2
Project number
1841
Site inspections
8

Schedule

The register lists Sidra 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 February 2020

100%+4.4 pts

  • Sidra 2 construction site, inspection photo 1, 13 February 2020
  • Sidra 2 construction site, inspection photo 2, 13 February 2020
  • Sidra 2 construction site, inspection photo 3, 13 February 2020
  • Sidra 2 construction site, inspection photo 4, 13 February 2020

5 November 2019

96%+5.1 pts

  • Sidra 2 construction site, inspection photo 1, 5 November 2019
  • Sidra 2 construction site, inspection photo 2, 5 November 2019
  • Sidra 2 construction site, inspection photo 3, 5 November 2019
  • Sidra 2 construction site, inspection photo 4, 5 November 2019

8 July 2019

90%+29 pts

  • Sidra 2 construction site, inspection photo 1, 8 July 2019
  • Sidra 2 construction site, inspection photo 2, 8 July 2019
  • Sidra 2 construction site, inspection photo 3, 8 July 2019
  • Sidra 2 construction site, inspection photo 4, 8 July 2019

11 March 2019

61%+19 pts

  • Sidra 2 construction site, inspection photo 1, 11 March 2019
  • Sidra 2 construction site, inspection photo 2, 11 March 2019
  • Sidra 2 construction site, inspection photo 3, 11 March 2019
  • Sidra 2 construction site, inspection photo 4, 11 March 2019

15 November 2018

43%+23 pts

  • Sidra 2 construction site, inspection photo 1, 15 November 2018
  • Sidra 2 construction site, inspection photo 2, 15 November 2018
  • Sidra 2 construction site, inspection photo 3, 15 November 2018
  • Sidra 2 construction site, inspection photo 4, 15 November 2018

7 May 2018

20%+11 pts

  • Sidra 2 construction site, inspection photo 1, 7 May 2018
  • Sidra 2 construction site, inspection photo 2, 7 May 2018
  • Sidra 2 construction site, inspection photo 3, 7 May 2018
  • Sidra 2 construction site, inspection photo 4, 7 May 2018

18 January 2018

8.8%+4.2 pts

  • Sidra 2 construction site, inspection photo 1, 18 January 2018
  • Sidra 2 construction site, inspection photo 2, 18 January 2018
  • Sidra 2 construction site, inspection photo 3, 18 January 2018
  • Sidra 2 construction site, inspection photo 4, 18 January 2018

3 August 2017

4.6%

  • Sidra 2 construction site, inspection photo 1, 3 August 2017
  • Sidra 2 construction site, inspection photo 2, 3 August 2017
  • Sidra 2 construction site, inspection photo 3, 3 August 2017
  • Sidra 2 construction site, inspection photo 4, 3 August 2017

All 79 site photos, by inspection date

Context

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sidra 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Sidra 2 handover date?
Construction of Sidra 2 is recorded as complete, with a registered completion date of June 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Sidra 2?
Sidra 2 was 100% built at the site inspection on 13 February 2020. The site has been inspected 8 times since August 2017. The Land Department took 79 site photos at its inspections.
Is Sidra 2 delayed?
The register lists construction as complete.
Who is building Sidra 2?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Sidra 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.