Maple III construction progress

The register lists Maple III in Dubai Hills - Maple 3 as complete, with a registered completion date of May 2020. Its last site inspection on record was in November 2020. The developer is Dubai Hills Estate.

100%

Built, at the site inspection of 25 November 2020

Construction complete

Registered completion date
May 2020
Construction started
October 2017
First registered
May 2017
Community
Dubai Hills - Maple 3
Units
562
Escrow bank
Mashreq Bank
Name in Arabic
Iii ميبل
Project number
1899
Site inspections
11

Schedule

The register lists Maple III as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 November 2020

100%+1.5 pts

  • Maple III construction site, inspection photo 1, 25 November 2020
  • Maple III construction site, inspection photo 2, 25 November 2020
  • Maple III construction site, inspection photo 3, 25 November 2020
  • Maple III construction site, inspection photo 4, 25 November 2020

30 September 2020

98%+3.3 pts

  • Maple III construction site, inspection photo 1, 30 September 2020
  • Maple III construction site, inspection photo 2, 30 September 2020
  • Maple III construction site, inspection photo 3, 30 September 2020
  • Maple III construction site, inspection photo 4, 30 September 2020

22 June 2020

95%+4.3 pts

  • Maple III construction site, inspection photo 1, 22 June 2020
  • Maple III construction site, inspection photo 2, 22 June 2020
  • Maple III construction site, inspection photo 3, 22 June 2020
  • Maple III construction site, inspection photo 4, 22 June 2020

5 March 2020

91%+11 pts

  • Maple III construction site, inspection photo 1, 5 March 2020
  • Maple III construction site, inspection photo 2, 5 March 2020
  • Maple III construction site, inspection photo 3, 5 March 2020
  • Maple III construction site, inspection photo 4, 5 March 2020

10 November 2019

80%+17 pts

  • Maple III construction site, inspection photo 1, 10 November 2019
  • Maple III construction site, inspection photo 2, 10 November 2019
  • Maple III construction site, inspection photo 3, 10 November 2019
  • Maple III construction site, inspection photo 4, 10 November 2019

8 July 2019

63%+12 pts

  • Maple III construction site, inspection photo 1, 8 July 2019
  • Maple III construction site, inspection photo 2, 8 July 2019
  • Maple III construction site, inspection photo 3, 8 July 2019
  • Maple III construction site, inspection photo 4, 8 July 2019

21 April 2019

52%+12 pts

  • Maple III construction site, inspection photo 1, 21 April 2019
  • Maple III construction site, inspection photo 2, 21 April 2019
  • Maple III construction site, inspection photo 3, 21 April 2019
  • Maple III construction site, inspection photo 4, 21 April 2019

8 January 2019

40%+18 pts

  • Maple III construction site, inspection photo 1, 8 January 2019
  • Maple III construction site, inspection photo 2, 8 January 2019
  • Maple III construction site, inspection photo 3, 8 January 2019
  • Maple III construction site, inspection photo 4, 8 January 2019

11 September 2018

22%+16 pts

  • Maple III construction site, inspection photo 1, 11 September 2018
  • Maple III construction site, inspection photo 2, 11 September 2018
  • Maple III construction site, inspection photo 3, 11 September 2018
  • Maple III construction site, inspection photo 4, 11 September 2018

7 May 2018

6.2%+4.5 pts

  • Maple III construction site, inspection photo 1, 7 May 2018
  • Maple III construction site, inspection photo 2, 7 May 2018
  • Maple III construction site, inspection photo 3, 7 May 2018
  • Maple III construction site, inspection photo 4, 7 May 2018

All 111 site photos, by inspection date

Context

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Maple III?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Maple III handover date?
Construction of Maple III is recorded as complete, with a registered completion date of May 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Maple III?
Maple III was 100% built at the site inspection on 25 November 2020. The site has been inspected 11 times since January 2018. The Land Department took 111 site photos at its inspections.
Is Maple III delayed?
The register lists construction as complete.
Who is building Maple III?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Maple III?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.