The Signature construction progress

The register lists The Signature in DownTown Dubai as complete, with a registered completion date of May 2013. Its last site inspection on record was in March 2013. The developer is Damac Star Properties.

100%

Built, at the site inspection of 4 March 2013

Construction complete

Registered completion date
May 2013
Construction started
March 2010
First registered
November 2008
Developer
Damac Star Properties
Units
357
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سيجنتشر
Project number
413
Site inspections
2

Schedule

The register lists The Signature as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201120122013
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 March 2013

93%+8.6 pts

  • The Signature construction site, inspection photo 1, 4 March 2013
  • The Signature construction site, inspection photo 2, 4 March 2013
  • The Signature construction site, inspection photo 3, 4 March 2013
  • The Signature construction site, inspection photo 4, 4 March 2013

27 September 2012

84%

  • The Signature construction site, inspection photo 1, 27 September 2012
  • The Signature construction site, inspection photo 2, 27 September 2012
  • The Signature construction site, inspection photo 3, 27 September 2012
  • The Signature construction site, inspection photo 4, 27 September 2012

All 22 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Own a unit in The Signature?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Signature handover date?
Construction of The Signature is recorded as complete, with a registered completion date of May 2013. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Signature?
The Signature was 100% built at the site inspection on 4 March 2013. The site has been inspected 2 times since September 2012. The Land Department took 22 site photos at its inspections.
Is The Signature delayed?
The register lists construction as complete.
Who is building The Signature?
The registered developer is Damac Star Properties.
Which bank holds the escrow account for The Signature?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.