Skip to content

The Distinction construction progress

The register lists The Distinction in DownTown Dubai as complete, with a registered completion date of February 2016. Its last site inspection on record was in January 2017. The developer is Damac Development.

100%

Built, at the site inspection of 15 January 2017

Construction complete

Registered completion date
February 2016
Construction started
August 2012
First registered
September 2012
Developer
Damac Development
Units
308
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
التمييز
Project number
1329
Site inspections
11

Schedule

The register lists The Distinction as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20132014201520162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 January 2017

100%+1.9 pts

  • The Distinction construction site, inspection photo 1, 15 January 2017
  • The Distinction construction site, inspection photo 2, 15 January 2017
  • The Distinction construction site, inspection photo 3, 15 January 2017
  • The Distinction construction site, inspection photo 4, 15 January 2017

31 August 2016

98%+8.1 pts

  • The Distinction construction site, inspection photo 1, 31 August 2016
  • The Distinction construction site, inspection photo 2, 31 August 2016
  • The Distinction construction site, inspection photo 3, 31 August 2016
  • The Distinction construction site, inspection photo 4, 31 August 2016

9 December 2015

90%+6.9 pts

  • The Distinction construction site, inspection photo 1, 9 December 2015
  • The Distinction construction site, inspection photo 2, 9 December 2015
  • The Distinction construction site, inspection photo 3, 9 December 2015
  • The Distinction construction site, inspection photo 4, 9 December 2015

25 August 2015

83%+8.4 pts

  • The Distinction construction site, inspection photo 1, 25 August 2015
  • The Distinction construction site, inspection photo 2, 25 August 2015
  • The Distinction construction site, inspection photo 3, 25 August 2015
  • The Distinction construction site, inspection photo 4, 25 August 2015

1 June 2015

75%+11 pts

  • The Distinction construction site, inspection photo 1, 1 June 2015
  • The Distinction construction site, inspection photo 2, 1 June 2015
  • The Distinction construction site, inspection photo 3, 1 June 2015
  • The Distinction construction site, inspection photo 4, 1 June 2015

19 March 2015

64%+18 pts

  • The Distinction construction site, inspection photo 1, 19 March 2015
  • The Distinction construction site, inspection photo 2, 19 March 2015
  • The Distinction construction site, inspection photo 3, 19 March 2015
  • The Distinction construction site, inspection photo 4, 19 March 2015

25 December 2014

45%+13 pts

  • The Distinction construction site, inspection photo 1, 25 December 2014
  • The Distinction construction site, inspection photo 2, 25 December 2014
  • The Distinction construction site, inspection photo 3, 25 December 2014
  • The Distinction construction site, inspection photo 4, 25 December 2014

17 September 2014

33%+6.5 pts

  • The Distinction construction site, inspection photo 1, 17 September 2014
  • The Distinction construction site, inspection photo 2, 17 September 2014
  • The Distinction construction site, inspection photo 3, 17 September 2014
  • The Distinction construction site, inspection photo 4, 17 September 2014

9 March 2014

26%+5.0 pts

  • The Distinction construction site, inspection photo 1, 9 March 2014
  • The Distinction construction site, inspection photo 2, 9 March 2014
  • The Distinction construction site, inspection photo 3, 9 March 2014
  • The Distinction construction site, inspection photo 4, 9 March 2014

10 November 2013

21%+7.3 pts

  • The Distinction construction site, inspection photo 1, 10 November 2013
  • The Distinction construction site, inspection photo 2, 10 November 2013
  • The Distinction construction site, inspection photo 3, 10 November 2013
  • The Distinction construction site, inspection photo 4, 10 November 2013

All 95 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Own a unit in The Distinction?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Distinction handover date?
Construction of The Distinction is recorded as complete, with a registered completion date of February 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Distinction?
The Distinction was 100% built at the site inspection on 15 January 2017. The site has been inspected 11 times since June 2013. The Land Department took 95 site photos at its inspections.
Is The Distinction delayed?
The register lists construction as complete.
Who is building The Distinction?
The registered developer is Damac Development.
Which bank holds the escrow account for The Distinction?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.