The Distinction construction photos

95 photos from 11 site inspections, newest first. The percentage is how much of The Distinction was built on the day of each visit.

15 January 2017100% built

31 August 201698% built

9 December 201590% built

25 August 201583% built

1 June 201575% built

19 March 201564% built

25 December 201445% built

17 September 201433% built

9 March 201426% built

10 November 201321% built

5 June 201314% built

Back to The Distinction construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.