Skip to content

Opulent Residences construction progress

Opulent Residences in DownTown Dubai is 8.5% built at the Land Department inspection of July 2026. Developer East & West Properties. Completion registered for December 2027.

8.5%

Built, at the Land Department site inspection of 27 July 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
March 2054
Construction started
January 2024
Registered with the Land Department
January 2024
Developer
East & West Properties
Units
230
Escrow bank
Emirates NBD
Name in Arabic
اوبولينت ريزيدنسز
Land Department project number
2887
Land Department site inspections
6

Schedule

Between October 2025 and July 2026 the site added about 0.3 points a month. At that rate it would finish around March 2054, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 July 2026

8.5%+1.1 pts

  • Opulent Residences construction site, Land Department inspection photo 1, 27 July 2026
  • Opulent Residences construction site, Land Department inspection photo 2, 27 July 2026
  • Opulent Residences construction site, Land Department inspection photo 3, 27 July 2026
  • Opulent Residences construction site, Land Department inspection photo 4, 27 July 2026

23 April 2026

7.4%+1.5 pts

  • Opulent Residences construction site, Land Department inspection photo 1, 23 April 2026
  • Opulent Residences construction site, Land Department inspection photo 2, 23 April 2026
  • Opulent Residences construction site, Land Department inspection photo 3, 23 April 2026
  • Opulent Residences construction site, Land Department inspection photo 4, 23 April 2026

10 October 2025

5.9%

  • Opulent Residences construction site, Land Department inspection photo 1, 10 October 2025
  • Opulent Residences construction site, Land Department inspection photo 2, 10 October 2025
  • Opulent Residences construction site, Land Department inspection photo 3, 10 October 2025
  • Opulent Residences construction site, Land Department inspection photo 4, 10 October 2025

26 June 2025

5.9%+2.6 pts

  • Opulent Residences construction site, Land Department inspection photo 1, 26 June 2025
  • Opulent Residences construction site, Land Department inspection photo 2, 26 June 2025
  • Opulent Residences construction site, Land Department inspection photo 3, 26 June 2025
  • Opulent Residences construction site, Land Department inspection photo 4, 26 June 2025

3 January 2025

3.2%+3.2 pts

  • Opulent Residences construction site, Land Department inspection photo 1, 3 January 2025
  • Opulent Residences construction site, Land Department inspection photo 2, 3 January 2025
  • Opulent Residences construction site, Land Department inspection photo 3, 3 January 2025

27 December 2023

0%

  • Opulent Residences construction site, Land Department inspection photo 1, 27 December 2023
  • Opulent Residences construction site, Land Department inspection photo 2, 27 December 2023

All 25 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 33% built on average.

East & West Properties has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Opulent Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Opulent Residences be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around March 2054. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Opulent Residences is built?
8.5%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 6 times since December 2023.
Is Opulent Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Opulent Residences?
The registered developer is East & West Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Opulent Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.