Opulent Residences construction progress
Opulent Residences in DownTown Dubai is 8.5% built at the Land Department inspection of July 2026. Developer East & West Properties. Completion registered for December 2027.
8.5%
Built, at the Land Department site inspection of 27 July 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- March 2054
- Construction started
- January 2024
- Registered with the Land Department
- January 2024
- Developer
- East & West Properties
- Community
- DownTown Dubai
- Units
- 230
- Escrow bank
- Emirates NBD
- Name in Arabic
- اوبولينت ريزيدنسز
- Land Department project number
- 2887
- Land Department site inspections
- 6
Schedule
Between October 2025 and July 2026 the site added about 0.3 points a month. At that rate it would finish around March 2054, more than three months after the December 2027 date registered with the Land Department.
Site inspections
27 July 2026
8.5%+1.1 pts
23 April 2026
7.4%+1.5 pts
10 October 2025
5.9%
26 June 2025
5.9%+2.6 pts
3 January 2025
3.2%+3.2 pts
27 December 2023
0%
Context
DownTown Dubai has 13 projects under construction, 33% built on average.
East & West Properties has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Opulent Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Opulent Residences be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around March 2054. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Opulent Residences is built?
- 8.5%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 6 times since December 2023.
- Is Opulent Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Opulent Residences?
- The registered developer is East & West Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Opulent Residences?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Euphoric ResidencesAlso by East & West Properties. 8.3%, Due December 2027.
- The St. Regis Residences, Downtown DubaiNearby in DownTown Dubai. 76%, Due December 2026.
- City Center ResidencesNearby in DownTown Dubai. 72%, Due September 2026, passed.
- Mercedes-Benz Places | BinghattiNearby in DownTown Dubai. 65%, Due December 2026.
- Baccarat Hotel And Residences, DubaiNearby in DownTown Dubai. 21%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.















.png&w=3840&q=75)
.png&w=3840&q=75)