Skip to content

Euphoric Residences construction progress

The registered completion date for Euphoric Residences in DownTown Dubai is December 2027. At the last site inspection, in July 2026, it was 8.3% built. The developer is East & West Properties.

8.3%

Built, at the site inspection of 27 July 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
October 2056
Construction started
January 2024
First registered
January 2024
Developer
East & West Properties
Units
276
Escrow bank
Emirates NBD
Name in Arabic
يوفوريك ريزدنسز
Project number
2886
Site inspections
6

Schedule

Between October 2025 and July 2026 the site added about 0.3 points a month. At that rate it would finish around October 2056, more than three months after its registered date of December 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 July 2026

8.3%+1.2 pts

  • Euphoric Residences construction site, inspection photo 1, 27 July 2026
  • Euphoric Residences construction site, inspection photo 2, 27 July 2026
  • Euphoric Residences construction site, inspection photo 3, 27 July 2026
  • Euphoric Residences construction site, inspection photo 4, 27 July 2026

30 April 2026

7.1%+1.3 pts

  • Euphoric Residences construction site, inspection photo 1, 30 April 2026
  • Euphoric Residences construction site, inspection photo 2, 30 April 2026
  • Euphoric Residences construction site, inspection photo 3, 30 April 2026
  • Euphoric Residences construction site, inspection photo 4, 30 April 2026

9 October 2025

5.9%+0.1 pts

  • Euphoric Residences construction site, inspection photo 1, 9 October 2025
  • Euphoric Residences construction site, inspection photo 2, 9 October 2025

26 June 2025

5.8%+1.1 pts

  • Euphoric Residences construction site, inspection photo 1, 26 June 2025
  • Euphoric Residences construction site, inspection photo 2, 26 June 2025
  • Euphoric Residences construction site, inspection photo 3, 26 June 2025

3 January 2025

4.7%+4.7 pts

  • Euphoric Residences construction site, inspection photo 1, 3 January 2025
  • Euphoric Residences construction site, inspection photo 2, 3 January 2025
  • Euphoric Residences construction site, inspection photo 3, 3 January 2025
  • Euphoric Residences construction site, inspection photo 4, 3 January 2025

27 December 2023

0%

  • Euphoric Residences construction site, inspection photo 1, 27 December 2023
  • Euphoric Residences construction site, inspection photo 2, 27 December 2023
  • Euphoric Residences construction site, inspection photo 3, 27 December 2023

All 23 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

East & West Properties has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Euphoric Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Euphoric Residences handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2056. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Euphoric Residences?
Euphoric Residences was 8.3% built at the site inspection on 27 July 2026. The site has been inspected 6 times since December 2023. The Land Department took 23 site photos at its inspections.
Is Euphoric Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Euphoric Residences?
The registered developer is East & West Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Euphoric Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.