Burj Royale construction progress

The register lists Burj Royale in DownTown Dubai as complete, with a registered completion date of October 2022. Its last site inspection on record was in November 2022. The developer is Old Town Views.

100%

Built, at the site inspection of 8 November 2022

Construction complete

Registered completion date
October 2022
Construction started
February 2019
First registered
November 2018
Developer
Old Town Views
Units
602
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
برج رويال
Project number
2112
Site inspections
12

Schedule

The register lists Burj Royale as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 November 2022

100%+4.9 pts

  • Burj Royale construction site, inspection photo 1, 8 November 2022
  • Burj Royale construction site, inspection photo 2, 8 November 2022
  • Burj Royale construction site, inspection photo 3, 8 November 2022
  • Burj Royale construction site, inspection photo 4, 8 November 2022

12 August 2022

95%+7.0 pts

  • Burj Royale construction site, inspection photo 1, 12 August 2022
  • Burj Royale construction site, inspection photo 2, 12 August 2022
  • Burj Royale construction site, inspection photo 3, 12 August 2022
  • Burj Royale construction site, inspection photo 4, 12 August 2022

14 January 2022

88%+8.0 pts

  • Burj Royale construction site, inspection photo 1, 14 January 2022
  • Burj Royale construction site, inspection photo 2, 14 January 2022
  • Burj Royale construction site, inspection photo 3, 14 January 2022
  • Burj Royale construction site, inspection photo 4, 14 January 2022

29 September 2021

80%+15 pts

  • Burj Royale construction site, inspection photo 1, 29 September 2021
  • Burj Royale construction site, inspection photo 2, 29 September 2021
  • Burj Royale construction site, inspection photo 3, 29 September 2021
  • Burj Royale construction site, inspection photo 4, 29 September 2021

21 June 2021

65%+15 pts

  • Burj Royale construction site, inspection photo 1, 21 June 2021
  • Burj Royale construction site, inspection photo 2, 21 June 2021
  • Burj Royale construction site, inspection photo 3, 21 June 2021
  • Burj Royale construction site, inspection photo 4, 21 June 2021

22 March 2021

50%+16 pts

  • Burj Royale construction site, inspection photo 1, 22 March 2021
  • Burj Royale construction site, inspection photo 2, 22 March 2021
  • Burj Royale construction site, inspection photo 3, 22 March 2021
  • Burj Royale construction site, inspection photo 4, 22 March 2021

29 December 2020

34%+13 pts

  • Burj Royale construction site, inspection photo 1, 29 December 2020
  • Burj Royale construction site, inspection photo 2, 29 December 2020
  • Burj Royale construction site, inspection photo 3, 29 December 2020
  • Burj Royale construction site, inspection photo 4, 29 December 2020

8 September 2020

22%+7.0 pts

  • Burj Royale construction site, inspection photo 1, 8 September 2020
  • Burj Royale construction site, inspection photo 2, 8 September 2020
  • Burj Royale construction site, inspection photo 3, 8 September 2020
  • Burj Royale construction site, inspection photo 4, 8 September 2020

27 May 2020

14%+6.5 pts

  • Burj Royale construction site, inspection photo 1, 27 May 2020
  • Burj Royale construction site, inspection photo 2, 27 May 2020
  • Burj Royale construction site, inspection photo 3, 27 May 2020
  • Burj Royale construction site, inspection photo 4, 27 May 2020

20 January 2020

8.0%+1.8 pts

  • Burj Royale construction site, inspection photo 1, 20 January 2020
  • Burj Royale construction site, inspection photo 2, 20 January 2020
  • Burj Royale construction site, inspection photo 3, 20 January 2020
  • Burj Royale construction site, inspection photo 4, 20 January 2020

All 115 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Own a unit in Burj Royale?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Burj Royale handover date?
Construction of Burj Royale is recorded as complete, with a registered completion date of October 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Burj Royale?
Burj Royale was 100% built at the site inspection on 8 November 2022. The site has been inspected 12 times since June 2019. The Land Department took 115 site photos at its inspections.
Is Burj Royale delayed?
The register lists construction as complete.
Who is building Burj Royale?
The registered developer is Old Town Views.
Which bank holds the escrow account for Burj Royale?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.