Burj Royale construction photos

115 photos from 12 site inspections, newest first. The percentage is how much of Burj Royale was built on the day of each visit.

8 November 2022100% built

12 August 202295% built

14 January 202288% built

29 September 202180% built

21 June 202165% built

22 March 202150% built

29 December 202034% built

8 September 202022% built

27 May 202014% built

20 January 20208.0% built

10 October 20196.2% built

27 June 20191.6% built

Back to Burj Royale construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.