Azha Downtown Residences construction progress

Azha Downtown Residences in DownTown Dubai is 27% built at the Land Department inspection of September 2026. Developer Azha Downtown Residences. Completion registered for August 2027.

27%

Built, at the Land Department site inspection of 23 September 2026

Running behind its date

Completion date (Land Department)
August 2027
Finish at recent pace
October 2030
Construction started
August 2024
Registered with the Land Department
June 2024
Developer
Azha Downtown Residences
Units
73
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ازهى داون تاون السكنية
Land Department project number
3129
Land Department site inspections
5

Schedule

Between November 2025 and September 2026 the site added about 1.5 points a month. At that rate it would finish around October 2030, more than three months after the August 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 September 2026

27%+12 pts

  • Azha Downtown Residences construction site, Land Department inspection photo 1, 23 September 2026
  • Azha Downtown Residences construction site, Land Department inspection photo 2, 23 September 2026
  • Azha Downtown Residences construction site, Land Department inspection photo 3, 23 September 2026
  • Azha Downtown Residences construction site, Land Department inspection photo 4, 23 September 2026

11 March 2026

15%+4.2 pts

  • Azha Downtown Residences construction site, Land Department inspection photo 1, 11 March 2026
  • Azha Downtown Residences construction site, Land Department inspection photo 2, 11 March 2026
  • Azha Downtown Residences construction site, Land Department inspection photo 3, 11 March 2026
  • Azha Downtown Residences construction site, Land Department inspection photo 4, 11 March 2026

4 November 2025

11%+2.7 pts

  • Azha Downtown Residences construction site, Land Department inspection photo 1, 4 November 2025
  • Azha Downtown Residences construction site, Land Department inspection photo 2, 4 November 2025
  • Azha Downtown Residences construction site, Land Department inspection photo 3, 4 November 2025
  • Azha Downtown Residences construction site, Land Department inspection photo 4, 4 November 2025

15 May 2025

8.3%+8.3 pts

  • Azha Downtown Residences construction site, Land Department inspection photo 1, 15 May 2025
  • Azha Downtown Residences construction site, Land Department inspection photo 2, 15 May 2025
  • Azha Downtown Residences construction site, Land Department inspection photo 3, 15 May 2025
  • Azha Downtown Residences construction site, Land Department inspection photo 4, 15 May 2025

6 June 2024

0%

  • Azha Downtown Residences construction site, Land Department inspection photo 1, 6 June 2024

All 24 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 33% built on average.

Own a unit in Azha Downtown Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azha Downtown Residences be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around October 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azha Downtown Residences is built?
27%, measured at the Land Department site inspection on 23 September 2026. The Land Department engineers have inspected the site 5 times since June 2024.
Is Azha Downtown Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Azha Downtown Residences?
The registered developer is Azha Downtown Residences.
Which bank holds the escrow account for Azha Downtown Residences?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.