Azha Downtown Residences construction photos

24 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Azha Downtown Residences was built on the day of each visit.

23 September 202627% built

11 March 202615% built

4 November 202511% built

15 May 20258.3% built

6 June 20240% built

Back to Azha Downtown Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.