City Walk Crestlane 3 construction progress
City Walk Crestlane 3 in City Walk is 4.6% built at the Land Department inspection of September 2026. Developer Citywalk Residential 1. Completion registered for December 2028.
4.6%
Built, at the Land Department site inspection of 15 September 2026
Running behind its date
- Completion date (Land Department)
- December 2028
- Finish at recent pace
- December 2043
- Construction started
- April 2025
- Registered with the Land Department
- February 2025
- Developer
- Citywalk Residential 1
- Community
- City Walk
- Units
- 195
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- سيتي ووك كريستلين 3
- Land Department project number
- 3531
- Land Department site inspections
- 6
Schedule
Between November 2025 and September 2026 the site added about 0.5 points a month. At that rate it would finish around December 2043, more than three months after the December 2028 date registered with the Land Department.
Site inspections
15 September 2026
4.6%+3.9 pts
16 June 2026
0.7%+0.7 pts
13 March 2026
0%
19 November 2025
0%+0.0 pts
25 August 2025
0%
31 January 2025
0%
Context
City Walk has 7 projects under construction, 21% built on average.
Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in City Walk Crestlane 3?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will City Walk Crestlane 3 be completed?
- The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around December 2043. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of City Walk Crestlane 3 is built?
- 4.6%, measured at the Land Department site inspection on 15 September 2026. The Land Department engineers have inspected the site 6 times since January 2025.
- Is City Walk Crestlane 3 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building City Walk Crestlane 3?
- The registered developer is Citywalk Residential 1. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for City Walk Crestlane 3?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Central Park PlazaAlso by Citywalk Residential 1. 44%, Due October 2026, passed.
- City Walk Northline 1Also by Citywalk Residential 1. 38%.
- City Walk Northline 2Also by Citywalk Residential 1. 37%.
- Verve City WalkAlso by Citywalk Residential 1. 14%, Due September 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)