Central Park Plaza construction progress
Central Park Plaza in City Walk was registered to complete in October 2026 and is still under construction. At the last site inspection, in September 2026, it was 44% built. The developer is Citywalk Residential 1.
44%
Built, at the site inspection of 1 September 2026
2 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- May 2028
- Construction started
- December 2023
- First registered
- October 2023
- Developer
- Citywalk Residential 1
- Community
- City Walk
- Units
- 212
- Escrow bank
- Emirates NBD
- Name in Arabic
- سنترال بارك بلازا
- Project number
- 2796
- Site inspections
- 9
Schedule
Central Park Plaza was registered to complete in October 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around May 2028.
Site inspections
1 September 2026
44%+9.0 pts
19 May 2026
35%+8.5 pts
13 February 2026
26%+9.7 pts
3 November 2025
16%+5.8 pts
6 August 2025
11%+3.7 pts
13 May 2025
7.0%+1.0 pts
5 February 2025
6.0%+0.7 pts
21 September 2024
5.3%+5.3 pts
4 October 2023
0%
Context
City Walk has 7 projects under construction, 24% built on average.
Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Central Park Plaza?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Central Park Plaza handover date?
- The registered completion date was October 2026, and the register still lists Central Park Plaza as under construction. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Central Park Plaza?
- Central Park Plaza was 44% built at the site inspection on 1 September 2026. The site has been inspected 9 times since October 2023. The Land Department took 49 site photos at its inspections.
- Is Central Park Plaza delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building Central Park Plaza?
- The registered developer is Citywalk Residential 1. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Central Park Plaza?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- City Walk Northline 1Also by Citywalk Residential 1. 46%.
- City Walk Northline 2Also by Citywalk Residential 1. 49%.
- Verve City WalkAlso by Citywalk Residential 1. 18%, Due September 2028.
- City Walk Crestlane 2Also by Citywalk Residential 1. 6.8%, Due December 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)







.jpg&w=3840&q=75)