Central Park Plaza construction progress

Central Park Plaza in City Walk was registered to complete in October 2026 and is still under construction. At the last site inspection, in September 2026, it was 44% built. The developer is Citywalk Residential 1.

44%

Built, at the site inspection of 1 September 2026

2 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
May 2028
Construction started
December 2023
First registered
October 2023
Community
City Walk
Units
212
Escrow bank
Emirates NBD
Name in Arabic
سنترال بارك بلازا
Project number
2796
Site inspections
9

Schedule

Central Park Plaza was registered to complete in October 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around May 2028.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 September 2026

44%+9.0 pts

  • Central Park Plaza construction site, inspection photo 1, 1 September 2026
  • Central Park Plaza construction site, inspection photo 2, 1 September 2026
  • Central Park Plaza construction site, inspection photo 3, 1 September 2026
  • Central Park Plaza construction site, inspection photo 4, 1 September 2026

19 May 2026

35%+8.5 pts

  • Central Park Plaza construction site, inspection photo 1, 19 May 2026
  • Central Park Plaza construction site, inspection photo 2, 19 May 2026
  • Central Park Plaza construction site, inspection photo 3, 19 May 2026
  • Central Park Plaza construction site, inspection photo 4, 19 May 2026

13 February 2026

26%+9.7 pts

  • Central Park Plaza construction site, inspection photo 1, 13 February 2026
  • Central Park Plaza construction site, inspection photo 2, 13 February 2026
  • Central Park Plaza construction site, inspection photo 3, 13 February 2026
  • Central Park Plaza construction site, inspection photo 4, 13 February 2026

3 November 2025

16%+5.8 pts

  • Central Park Plaza construction site, inspection photo 1, 3 November 2025
  • Central Park Plaza construction site, inspection photo 2, 3 November 2025
  • Central Park Plaza construction site, inspection photo 3, 3 November 2025
  • Central Park Plaza construction site, inspection photo 4, 3 November 2025

6 August 2025

11%+3.7 pts

  • Central Park Plaza construction site, inspection photo 1, 6 August 2025
  • Central Park Plaza construction site, inspection photo 2, 6 August 2025
  • Central Park Plaza construction site, inspection photo 3, 6 August 2025
  • Central Park Plaza construction site, inspection photo 4, 6 August 2025

13 May 2025

7.0%+1.0 pts

  • Central Park Plaza construction site, inspection photo 1, 13 May 2025
  • Central Park Plaza construction site, inspection photo 2, 13 May 2025
  • Central Park Plaza construction site, inspection photo 3, 13 May 2025
  • Central Park Plaza construction site, inspection photo 4, 13 May 2025

5 February 2025

6.0%+0.7 pts

  • Central Park Plaza construction site, inspection photo 1, 5 February 2025
  • Central Park Plaza construction site, inspection photo 2, 5 February 2025
  • Central Park Plaza construction site, inspection photo 3, 5 February 2025

21 September 2024

5.3%+5.3 pts

  • Central Park Plaza construction site, inspection photo 1, 21 September 2024
  • Central Park Plaza construction site, inspection photo 2, 21 September 2024
  • Central Park Plaza construction site, inspection photo 3, 21 September 2024
  • Central Park Plaza construction site, inspection photo 4, 21 September 2024

4 October 2023

0%

  • Central Park Plaza construction site, inspection photo 1, 4 October 2023
  • Central Park Plaza construction site, inspection photo 2, 4 October 2023
  • Central Park Plaza construction site, inspection photo 3, 4 October 2023

All 49 site photos, by inspection date

Context

City Walk has 7 projects under construction, 24% built on average.

Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Central Park Plaza?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Central Park Plaza handover date?
The registered completion date was October 2026, and the register still lists Central Park Plaza as under construction. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Central Park Plaza?
Central Park Plaza was 44% built at the site inspection on 1 September 2026. The site has been inspected 9 times since October 2023. The Land Department took 49 site photos at its inspections.
Is Central Park Plaza delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building Central Park Plaza?
The registered developer is Citywalk Residential 1. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Central Park Plaza?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.