City Walk Northline 1 construction progress
City Walk Northline 1 in City Walk is 38% built at the Land Department inspection of August 2026. Developer Citywalk Residential 1.
38%
Built, at the Land Department site inspection of 19 August 2026
- Finish at recent pace
- July 2028
- Construction started
- August 2024
- Registered with the Land Department
- March 2024
- Developer
- Citywalk Residential 1
- Community
- City Walk
- Units
- 115
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- سيتي ووك نورث لاين 1
- Land Department project number
- 2970
- Land Department site inspections
- 7
Schedule
Since August 2025 City Walk Northline 1 has added about 2.7 points a month. At that rate the site reaches 100% around July 2028. The Land Department has no completion date on record to compare it with.
Site inspections
19 August 2026
38%+11 pts
18 May 2026
27%+12 pts
9 February 2026
14%+7.7 pts
19 November 2025
6.8%+0.8 pts
25 August 2025
6.0%+0.2 pts
11 February 2025
5.8%+5.8 pts
26 February 2024
0%
Context
City Walk has 7 projects under construction, 21% built on average.
Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in City Walk Northline 1?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will City Walk Northline 1 be completed?
- The Land Department has no completion date on record for City Walk Northline 1 yet.
- How much of City Walk Northline 1 is built?
- 38%, measured at the Land Department site inspection on 19 August 2026. The Land Department engineers have inspected the site 7 times since February 2024.
- Who is building City Walk Northline 1?
- The registered developer is Citywalk Residential 1. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for City Walk Northline 1?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Central Park PlazaAlso by Citywalk Residential 1. 44%, Due October 2026, passed.
- City Walk Northline 2Also by Citywalk Residential 1. 37%.
- Verve City WalkAlso by Citywalk Residential 1. 14%, Due September 2028.
- City Walk Crestlane 2Also by Citywalk Residential 1. 6.8%, Due December 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)