City Walk Crestlane 3 construction photos
23 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of City Walk Crestlane 3 was built on the day of each visit.
15 September 20264.6% built
16 June 20260.7% built
13 March 20260% built
19 November 20250% built
25 August 20250% built
31 January 20250% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.