Verve City Walk construction progress
Verve City Walk in City Walk is 14% built at the Land Department inspection of August 2026. Developer Citywalk Residential 1. Completion registered for September 2028.
14%
Built, at the Land Department site inspection of 4 August 2026
Running behind its date
- Completion date (Land Department)
- September 2028
- Finish at recent pace
- May 2035
- Construction started
- November 2024
- Registered with the Land Department
- July 2024
- Developer
- Citywalk Residential 1
- Community
- City Walk
- Units
- 440
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- فيرف سيتي ووك
- Land Department project number
- 3152
- Land Department site inspections
- 7
Schedule
Between August 2025 and August 2026 the site added about 0.8 points a month. At that rate it would finish around May 2035, more than three months after the September 2028 date registered with the Land Department.
Site inspections
4 August 2026
14%+3.0 pts
7 May 2026
11%+2.9 pts
30 January 2026
7.9%+0.9 pts
31 October 2025
7.0%+3.1 pts
5 August 2025
3.9%+3.4 pts
5 May 2025
0.5%+0.5 pts
27 June 2024
0%
Context
City Walk has 7 projects under construction, 21% built on average.
Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Verve City Walk?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Verve City Walk be completed?
- The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around May 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Verve City Walk is built?
- 14%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 7 times since June 2024.
- Is Verve City Walk delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building Verve City Walk?
- The registered developer is Citywalk Residential 1. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Verve City Walk?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Central Park PlazaAlso by Citywalk Residential 1. 44%, Due October 2026, passed.
- City Walk Northline 1Also by Citywalk Residential 1. 38%.
- City Walk Northline 2Also by Citywalk Residential 1. 37%.
- City Walk Crestlane 2Also by Citywalk Residential 1. 6.8%, Due December 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.











.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)