Verve City Walk construction progress

Verve City Walk in City Walk is 14% built at the Land Department inspection of August 2026. Developer Citywalk Residential 1. Completion registered for September 2028.

14%

Built, at the Land Department site inspection of 4 August 2026

Running behind its date

Completion date (Land Department)
September 2028
Finish at recent pace
May 2035
Construction started
November 2024
Registered with the Land Department
July 2024
Community
City Walk
Units
440
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
فيرف سيتي ووك
Land Department project number
3152
Land Department site inspections
7

Schedule

Between August 2025 and August 2026 the site added about 0.8 points a month. At that rate it would finish around May 2035, more than three months after the September 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

4 August 2026

14%+3.0 pts

  • Verve City Walk construction site, Land Department inspection photo 1, 4 August 2026
  • Verve City Walk construction site, Land Department inspection photo 2, 4 August 2026
  • Verve City Walk construction site, Land Department inspection photo 3, 4 August 2026
  • Verve City Walk construction site, Land Department inspection photo 4, 4 August 2026

7 May 2026

11%+2.9 pts

  • Verve City Walk construction site, Land Department inspection photo 1, 7 May 2026
  • Verve City Walk construction site, Land Department inspection photo 2, 7 May 2026
  • Verve City Walk construction site, Land Department inspection photo 3, 7 May 2026
  • Verve City Walk construction site, Land Department inspection photo 4, 7 May 2026

30 January 2026

7.9%+0.9 pts

  • Verve City Walk construction site, Land Department inspection photo 1, 30 January 2026
  • Verve City Walk construction site, Land Department inspection photo 2, 30 January 2026
  • Verve City Walk construction site, Land Department inspection photo 3, 30 January 2026

31 October 2025

7.0%+3.1 pts

  • Verve City Walk construction site, Land Department inspection photo 1, 31 October 2025
  • Verve City Walk construction site, Land Department inspection photo 2, 31 October 2025
  • Verve City Walk construction site, Land Department inspection photo 3, 31 October 2025

5 August 2025

3.9%+3.4 pts

  • Verve City Walk construction site, Land Department inspection photo 1, 5 August 2025
  • Verve City Walk construction site, Land Department inspection photo 2, 5 August 2025
  • Verve City Walk construction site, Land Department inspection photo 3, 5 August 2025
  • Verve City Walk construction site, Land Department inspection photo 4, 5 August 2025

5 May 2025

0.5%+0.5 pts

  • Verve City Walk construction site, Land Department inspection photo 1, 5 May 2025
  • Verve City Walk construction site, Land Department inspection photo 2, 5 May 2025
  • Verve City Walk construction site, Land Department inspection photo 3, 5 May 2025
  • Verve City Walk construction site, Land Department inspection photo 4, 5 May 2025

27 June 2024

0%

  • Verve City Walk construction site, Land Department inspection photo 1, 27 June 2024
  • Verve City Walk construction site, Land Department inspection photo 2, 27 June 2024

All 26 site photos, by inspection date

Context

City Walk has 7 projects under construction, 21% built on average.

Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Verve City Walk?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Verve City Walk be completed?
The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around May 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Verve City Walk is built?
14%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 7 times since June 2024.
Is Verve City Walk delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Verve City Walk?
The registered developer is Citywalk Residential 1. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Verve City Walk?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.