Verve City Walk construction progress

The registered completion date for Verve City Walk in City Walk is September 2028. At the last site inspection, in November 2026, it was 18% built. The developer is Citywalk Residential 1.

18%

Built, at the site inspection of 4 November 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
March 2033
Construction started
November 2024
First registered
July 2024
Community
City Walk
Units
440
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
فيرف سيتي ووك
Project number
3152
Site inspections
8

Schedule

Between January 2026 and November 2026 the site added about 1.1 points a month. At that rate it would finish around March 2033, more than three months after its registered date of September 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 November 2026

18%+4.0 pts

  • Verve City Walk construction site, inspection photo 1, 4 November 2026
  • Verve City Walk construction site, inspection photo 2, 4 November 2026
  • Verve City Walk construction site, inspection photo 3, 4 November 2026
  • Verve City Walk construction site, inspection photo 4, 4 November 2026

4 August 2026

14%+3.0 pts

  • Verve City Walk construction site, inspection photo 1, 4 August 2026
  • Verve City Walk construction site, inspection photo 2, 4 August 2026
  • Verve City Walk construction site, inspection photo 3, 4 August 2026
  • Verve City Walk construction site, inspection photo 4, 4 August 2026

7 May 2026

11%+2.9 pts

  • Verve City Walk construction site, inspection photo 1, 7 May 2026
  • Verve City Walk construction site, inspection photo 2, 7 May 2026
  • Verve City Walk construction site, inspection photo 3, 7 May 2026
  • Verve City Walk construction site, inspection photo 4, 7 May 2026

30 January 2026

7.9%+0.9 pts

  • Verve City Walk construction site, inspection photo 1, 30 January 2026
  • Verve City Walk construction site, inspection photo 2, 30 January 2026
  • Verve City Walk construction site, inspection photo 3, 30 January 2026

31 October 2025

7.0%+3.1 pts

  • Verve City Walk construction site, inspection photo 1, 31 October 2025
  • Verve City Walk construction site, inspection photo 2, 31 October 2025
  • Verve City Walk construction site, inspection photo 3, 31 October 2025

5 August 2025

3.9%+3.4 pts

  • Verve City Walk construction site, inspection photo 1, 5 August 2025
  • Verve City Walk construction site, inspection photo 2, 5 August 2025
  • Verve City Walk construction site, inspection photo 3, 5 August 2025
  • Verve City Walk construction site, inspection photo 4, 5 August 2025

5 May 2025

0.5%+0.5 pts

  • Verve City Walk construction site, inspection photo 1, 5 May 2025
  • Verve City Walk construction site, inspection photo 2, 5 May 2025
  • Verve City Walk construction site, inspection photo 3, 5 May 2025
  • Verve City Walk construction site, inspection photo 4, 5 May 2025

27 June 2024

0%

  • Verve City Walk construction site, inspection photo 1, 27 June 2024
  • Verve City Walk construction site, inspection photo 2, 27 June 2024

All 33 site photos, by inspection date

Context

City Walk has 7 projects under construction, 24% built on average.

Citywalk Residential 1 has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Verve City Walk?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Verve City Walk handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Verve City Walk?
Verve City Walk was 18% built at the site inspection on 4 November 2026. The site has been inspected 8 times since June 2024. The Land Department took 33 site photos at its inspections.
Is Verve City Walk delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Verve City Walk?
The registered developer is Citywalk Residential 1. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Verve City Walk?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.