Skip to content

Atelis At D3 construction progress

The registered completion date for Atelis At D3 in Business Park is August 2029. At the last site inspection, in October 2026, it was 1.4% built. The developer is Dhre 2 Bts.

1.4%

Built, at the site inspection of 8 October 2026

Running behind its date

Registered completion date
August 2029
Finish at recent pace
August 2082
Construction started
August 2025
First registered
June 2025
Developer
Dhre 2 Bts
Community
Business Park
Units
280
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
أتيليس في حي دبي للتصميم
Project number
3750
Site inspections
5

Schedule

Between December 2025 and October 2026 the site added about 0.1 points a month. At that rate it would finish around August 2082, more than three months after its registered date of August 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2026

1.4%+0.5 pts

  • Atelis At D3 construction site, inspection photo 1, 8 October 2026
  • Atelis At D3 construction site, inspection photo 2, 8 October 2026
  • Atelis At D3 construction site, inspection photo 3, 8 October 2026
  • Atelis At D3 construction site, inspection photo 4, 8 October 2026

6 July 2026

1.0%+0.9 pts

  • Atelis At D3 construction site, inspection photo 1, 6 July 2026
  • Atelis At D3 construction site, inspection photo 2, 6 July 2026
  • Atelis At D3 construction site, inspection photo 3, 6 July 2026
  • Atelis At D3 construction site, inspection photo 4, 6 July 2026

23 March 2026

0.1%+0.0 pts

  • Atelis At D3 construction site, inspection photo 1, 23 March 2026
  • Atelis At D3 construction site, inspection photo 2, 23 March 2026
  • Atelis At D3 construction site, inspection photo 3, 23 March 2026
  • Atelis At D3 construction site, inspection photo 4, 23 March 2026

18 December 2025

0%+0.0 pts

  • Atelis At D3 construction site, inspection photo 1, 18 December 2025
  • Atelis At D3 construction site, inspection photo 2, 18 December 2025
  • Atelis At D3 construction site, inspection photo 3, 18 December 2025
  • Atelis At D3 construction site, inspection photo 4, 18 December 2025

17 June 2025

0%

  • Atelis At D3 construction site, inspection photo 1, 17 June 2025
  • Atelis At D3 construction site, inspection photo 2, 17 June 2025

All 21 site photos, by inspection date

Context

Business Park has 2 projects under construction, 21% built on average.

Dhre 2 Bts has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Atelis At D3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Atelis At D3 handover date?
The registered completion date is August 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2082. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Atelis At D3?
Atelis At D3 was 1.4% built at the site inspection on 8 October 2026. The site has been inspected 5 times since June 2025. The Land Department took 21 site photos at its inspections.
Is Atelis At D3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2029.
Who is building Atelis At D3?
The registered developer is Dhre 2 Bts. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Atelis At D3?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.