Helvetia Verde construction progress

The registered completion date for Helvetia Verde in Bukadra is November 2027. At the last site inspection, in July 2026, it was 0.6% built. The developer is D H G Property Development.

0.6%

Built, at the site inspection of 6 July 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
November 2163
Construction started
January 2026
First registered
October 2025
Developer
D H G Property Development
Community
Bukadra
Units
109
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
هيلفيتيا فيردي
Project number
4057
Site inspections
2

Schedule

Between August 2025 and July 2026 the site added about 0.1 points a month. At that rate it would finish around November 2163, more than three months after its registered date of November 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 July 2026

0.6%+0.6 pts

  • Helvetia Verde construction site, inspection photo 1, 6 July 2026
  • Helvetia Verde construction site, inspection photo 2, 6 July 2026
  • Helvetia Verde construction site, inspection photo 3, 6 July 2026
  • Helvetia Verde construction site, inspection photo 4, 6 July 2026

27 August 2025

0%

  • Helvetia Verde construction site, inspection photo 1, 27 August 2025
  • Helvetia Verde construction site, inspection photo 2, 27 August 2025

All 6 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 27% built on average.

D H G Property Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Helvetia Verde?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Helvetia Verde handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2163. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Helvetia Verde?
Helvetia Verde was 0.6% built at the site inspection on 6 July 2026. The site has been inspected 2 times since August 2025. The Land Department took 6 site photos at its inspections.
Is Helvetia Verde delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Helvetia Verde?
The registered developer is D H G Property Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Helvetia Verde?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.