Arabian Ranches - Samara Community construction progress
The register lists Arabian Ranches - Samara Community in Arabian Ranches II - Samara as complete, with a registered completion date of October 2017. Its last site inspection on record was in September 2018. The developer is Emaar Development.
100%
Built, at the site inspection of 23 September 2018
Construction complete
- Registered completion date
- October 2017
- Construction started
- May 2013
- First registered
- February 2013
- Developer
- Emaar Development
- Community
- Arabian Ranches II - Samara
- Units
- 177
- Escrow bank
- Mashreq Bank
- Name in Arabic
- المرابع العربية - مجتمع سمارا
- Project number
- 1335
- Site inspections
- 10
Schedule
The register lists Arabian Ranches - Samara Community as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
23 September 2018
100%+3.8 pts
27 February 2018
96%+0.5 pts
19 December 2017
96%+5.6 pts
20 August 2017
90%+19 pts
16 May 2017
71%+14 pts
14 February 2017
57%+27 pts
22 September 2016
30%+19 pts
22 December 2015
11%
14 July 2015
11%+3.6 pts
22 December 2014
7.4%
Context
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Arabian Ranches - Samara Community?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Arabian Ranches - Samara Community handover date?
- Construction of Arabian Ranches - Samara Community is recorded as complete, with a registered completion date of October 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Arabian Ranches - Samara Community?
- Arabian Ranches - Samara Community was 100% built at the site inspection on 23 September 2018. The site has been inspected 10 times since December 2014. The Land Department took 90 site photos at its inspections.
- Is Arabian Ranches - Samara Community delayed?
- The register lists construction as complete.
- Who is building Arabian Ranches - Samara Community?
- The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
- Which bank holds the escrow account for Arabian Ranches - Samara Community?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.