Arabian Ranches - Palma Community construction progress

The register lists Arabian Ranches - Palma Community in Arabian Ranches II - Palma as complete, with a registered completion date of February 2016. Its last site inspection on record was in May 2016. The developer is Emaar Properties.

100%

Built, at the site inspection of 10 May 2016

Construction complete

Registered completion date
February 2016
Construction started
February 2014
First registered
September 2013
Community
Arabian Ranches II - Palma
Units
122
Escrow bank
Emirates NBD
Name in Arabic
أرابيان رانشز - مجمع بالما
Project number
1377
Site inspections
7

Schedule

The register lists Arabian Ranches - Palma Community as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 May 2016

100%+14 pts

  • Arabian Ranches - Palma Community construction site, inspection photo 1, 10 May 2016
  • Arabian Ranches - Palma Community construction site, inspection photo 2, 10 May 2016
  • Arabian Ranches - Palma Community construction site, inspection photo 3, 10 May 2016
  • Arabian Ranches - Palma Community construction site, inspection photo 4, 10 May 2016

22 December 2015

86%+23 pts

  • Arabian Ranches - Palma Community construction site, inspection photo 1, 22 December 2015
  • Arabian Ranches - Palma Community construction site, inspection photo 2, 22 December 2015
  • Arabian Ranches - Palma Community construction site, inspection photo 3, 22 December 2015
  • Arabian Ranches - Palma Community construction site, inspection photo 4, 22 December 2015

14 September 2015

63%+22 pts

  • Arabian Ranches - Palma Community construction site, inspection photo 1, 14 September 2015
  • Arabian Ranches - Palma Community construction site, inspection photo 2, 14 September 2015
  • Arabian Ranches - Palma Community construction site, inspection photo 3, 14 September 2015
  • Arabian Ranches - Palma Community construction site, inspection photo 4, 14 September 2015

6 April 2015

41%+26 pts

  • Arabian Ranches - Palma Community construction site, inspection photo 1, 6 April 2015
  • Arabian Ranches - Palma Community construction site, inspection photo 2, 6 April 2015
  • Arabian Ranches - Palma Community construction site, inspection photo 3, 6 April 2015
  • Arabian Ranches - Palma Community construction site, inspection photo 4, 6 April 2015

22 December 2014

15%

  • Arabian Ranches - Palma Community construction site, inspection photo 1, 22 December 2014
  • Arabian Ranches - Palma Community construction site, inspection photo 2, 22 December 2014
  • Arabian Ranches - Palma Community construction site, inspection photo 3, 22 December 2014
  • Arabian Ranches - Palma Community construction site, inspection photo 4, 22 December 2014

19 October 2014

70%

  • Arabian Ranches - Palma Community construction site, inspection photo 1, 19 October 2014
  • Arabian Ranches - Palma Community construction site, inspection photo 2, 19 October 2014
  • Arabian Ranches - Palma Community construction site, inspection photo 3, 19 October 2014
  • Arabian Ranches - Palma Community construction site, inspection photo 4, 19 October 2014

10 June 2014

93%

  • Arabian Ranches - Palma Community construction site, inspection photo 1, 10 June 2014
  • Arabian Ranches - Palma Community construction site, inspection photo 2, 10 June 2014
  • Arabian Ranches - Palma Community construction site, inspection photo 3, 10 June 2014
  • Arabian Ranches - Palma Community construction site, inspection photo 4, 10 June 2014

All 56 site photos, by inspection date

Context

Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Arabian Ranches - Palma Community?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Arabian Ranches - Palma Community handover date?
Construction of Arabian Ranches - Palma Community is recorded as complete, with a registered completion date of February 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Arabian Ranches - Palma Community?
Arabian Ranches - Palma Community was 100% built at the site inspection on 10 May 2016. The site has been inspected 7 times since June 2014. The Land Department took 56 site photos at its inspections.
Is Arabian Ranches - Palma Community delayed?
The register lists construction as complete.
Who is building Arabian Ranches - Palma Community?
The registered developer is Emaar Properties. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Arabian Ranches - Palma Community?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.