Ar II Camelia construction progress

The register lists Ar II Camelia in Arabian Ranches II - Camelia as complete, with a registered completion date of January 2022. Its last site inspection on record was in December 2021. The developer is Emaar Development.

100%

Built, at the site inspection of 12 December 2021

Construction complete

Registered completion date
January 2022
Construction started
January 2019
First registered
November 2018
Community
Arabian Ranches II - Camelia
Units
259
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
كاميليا Ii المرابع العربية
Project number
2109
Site inspections
10

Schedule

The register lists Ar II Camelia as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 December 2021

100%+9.5 pts

  • Ar II Camelia construction site, inspection photo 1, 12 December 2021
  • Ar II Camelia construction site, inspection photo 2, 12 December 2021
  • Ar II Camelia construction site, inspection photo 3, 12 December 2021
  • Ar II Camelia construction site, inspection photo 4, 12 December 2021

13 September 2021

90%+8.4 pts

  • Ar II Camelia construction site, inspection photo 1, 13 September 2021
  • Ar II Camelia construction site, inspection photo 2, 13 September 2021
  • Ar II Camelia construction site, inspection photo 3, 13 September 2021
  • Ar II Camelia construction site, inspection photo 4, 13 September 2021

1 June 2021

82%+17 pts

  • Ar II Camelia construction site, inspection photo 1, 1 June 2021
  • Ar II Camelia construction site, inspection photo 2, 1 June 2021
  • Ar II Camelia construction site, inspection photo 3, 1 June 2021
  • Ar II Camelia construction site, inspection photo 4, 1 June 2021

11 February 2021

65%+13 pts

  • Ar II Camelia construction site, inspection photo 1, 11 February 2021
  • Ar II Camelia construction site, inspection photo 2, 11 February 2021
  • Ar II Camelia construction site, inspection photo 3, 11 February 2021
  • Ar II Camelia construction site, inspection photo 4, 11 February 2021

13 October 2020

52%+12 pts

  • Ar II Camelia construction site, inspection photo 1, 13 October 2020
  • Ar II Camelia construction site, inspection photo 2, 13 October 2020
  • Ar II Camelia construction site, inspection photo 3, 13 October 2020
  • Ar II Camelia construction site, inspection photo 4, 13 October 2020

8 July 2020

40%+12 pts

  • Ar II Camelia construction site, inspection photo 1, 8 July 2020
  • Ar II Camelia construction site, inspection photo 2, 8 July 2020
  • Ar II Camelia construction site, inspection photo 3, 8 July 2020
  • Ar II Camelia construction site, inspection photo 4, 8 July 2020

26 March 2020

28%+17 pts

  • Ar II Camelia construction site, inspection photo 1, 26 March 2020
  • Ar II Camelia construction site, inspection photo 2, 26 March 2020
  • Ar II Camelia construction site, inspection photo 3, 26 March 2020
  • Ar II Camelia construction site, inspection photo 4, 26 March 2020

16 December 2019

12%+7.0 pts

  • Ar II Camelia construction site, inspection photo 1, 16 December 2019
  • Ar II Camelia construction site, inspection photo 2, 16 December 2019
  • Ar II Camelia construction site, inspection photo 3, 16 December 2019
  • Ar II Camelia construction site, inspection photo 4, 16 December 2019

27 August 2019

4.5%+0.2 pts

  • Ar II Camelia construction site, inspection photo 1, 27 August 2019
  • Ar II Camelia construction site, inspection photo 2, 27 August 2019
  • Ar II Camelia construction site, inspection photo 3, 27 August 2019
  • Ar II Camelia construction site, inspection photo 4, 27 August 2019

22 May 2019

4.3%

  • Ar II Camelia construction site, inspection photo 1, 22 May 2019
  • Ar II Camelia construction site, inspection photo 2, 22 May 2019
  • Ar II Camelia construction site, inspection photo 3, 22 May 2019
  • Ar II Camelia construction site, inspection photo 4, 22 May 2019

All 81 site photos, by inspection date

Context

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Ar II Camelia?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Ar II Camelia handover date?
Construction of Ar II Camelia is recorded as complete, with a registered completion date of January 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Ar II Camelia?
Ar II Camelia was 100% built at the site inspection on 12 December 2021. The site has been inspected 10 times since May 2019. The Land Department took 81 site photos at its inspections.
Is Ar II Camelia delayed?
The register lists construction as complete.
Who is building Ar II Camelia?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Ar II Camelia?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.