Skip to content

Reem - Mira Oasis Community Phase 3 construction progress

The register lists Reem - Mira Oasis Community Phase 3 in Al Yelayiss 1 as complete, with a registered completion date of January 2020. Its last site inspection on record was in January 2020. The developer is Al Aryam Phase Two.

100%

Built, at the site inspection of 19 January 2020

Construction complete

Registered completion date
January 2020
Construction started
June 2016
First registered
April 2014
Developer
Al Aryam Phase Two
Community
Al Yelayiss 1
Units
483
Escrow bank
Dubai Islamic Bank
Name in Arabic
ريم - ميرا أويس
Project number
1500
Site inspections
16

Schedule

The register lists Reem - Mira Oasis Community Phase 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20162017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 January 2020

100%+1.3 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 19 January 2020
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 19 January 2020
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 19 January 2020
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 19 January 2020

22 December 2019

99%+5.0 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 22 December 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 22 December 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 22 December 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 22 December 2019

17 October 2019

94%+12 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 17 October 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 17 October 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 17 October 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 17 October 2019

11 July 2019

82%+4.2 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 11 July 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 11 July 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 11 July 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 11 July 2019

20 March 2019

78%+8.9 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 20 March 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 20 March 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 20 March 2019
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 20 March 2019

21 October 2018

69%+2.8 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 21 October 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 21 October 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 21 October 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 21 October 2018

29 August 2018

66%+14 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 29 August 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 29 August 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 29 August 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 29 August 2018

6 May 2018

52%+8.5 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 6 May 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 6 May 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 6 May 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 6 May 2018

20 March 2018

43%+18 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 20 March 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 20 March 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 20 March 2018
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 20 March 2018

22 November 2017

25%+11 pts

  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 1, 22 November 2017
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 2, 22 November 2017
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 3, 22 November 2017
  • Reem - Mira Oasis Community Phase 3 construction site, inspection photo 4, 22 November 2017

All 148 site photos, by inspection date

Context

Al Yelayiss 1 has 18 projects under construction, 6.5% built on average.

Own a unit in Reem - Mira Oasis Community Phase 3?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Reem - Mira Oasis Community Phase 3 handover date?
Construction of Reem - Mira Oasis Community Phase 3 is recorded as complete, with a registered completion date of January 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Reem - Mira Oasis Community Phase 3?
Reem - Mira Oasis Community Phase 3 was 100% built at the site inspection on 19 January 2020. The site has been inspected 16 times since June 2015. The Land Department took 148 site photos at its inspections.
Is Reem - Mira Oasis Community Phase 3 delayed?
The register lists construction as complete.
Who is building Reem - Mira Oasis Community Phase 3?
The registered developer is Al Aryam Phase Two.
Which bank holds the escrow account for Reem - Mira Oasis Community Phase 3?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.