Damac Sun City construction progress
The registered completion date for Damac Sun City in Al Yelayiss 1 is March 2028. At the last site inspection, in September 2026, it was 37% built. The developer is Damac Elite Investment Co.
37%
Built, at the site inspection of 24 September 2026
On pace for its date
- Registered completion date
- March 2028
- Finish at recent pace
- February 2028
- Construction started
- December 2024
- First registered
- September 2024
- Developer
- Damac Elite Investment Co
- Community
- Al Yelayiss 1
- Units
- 770
- Escrow bank
- Emirates NBD
- Name in Arabic
- داماك صن سيتي
- Project number
- 3268
- Site inspections
- 6
Schedule
Since January 2026 Damac Sun City has added about 3.7 points a month. That puts 100% around February 2028, within three months of its registered completion date of March 2028.
Site inspections
24 September 2026
37%+17 pts
20 May 2026
19%+12 pts
27 January 2026
7.1%+3.2 pts
20 August 2025
3.9%+2.0 pts
15 April 2025
1.9%+1.9 pts
29 August 2024
0%
Context
Al Yelayiss 1 has 18 projects under construction, 6.5% built on average.
Damac Elite Investment Co has 20 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Damac Sun City?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Damac Sun City handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Damac Sun City?
- Damac Sun City was 37% built at the site inspection on 24 September 2026. The site has been inspected 6 times since August 2024. The Land Department took 41 site photos at its inspections.
- Is Damac Sun City delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2028.
- Who is building Damac Sun City?
- The registered developer is Damac Elite Investment Co. It has 19 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Sun City?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Islands - Maldives 1Also by Damac Elite Investment Co. 6.6%, Due December 2028.
- Damac Islands - Maldives 2Also by Damac Elite Investment Co. 14%, Due December 2028.
- Damac Islands - Maldives 3Also by Damac Elite Investment Co. 12%, Due December 2028.
- Damac Islands - Bali 1Also by Damac Elite Investment Co. 7.0%, Due December 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)