Damac Sun City construction progress

Damac Sun City in Al Yelayiss 1 is 37% built at the Land Department inspection of September 2026. Developer Damac Elite Investment Co. Completion registered for March 2028.

37%

Built, at the Land Department site inspection of 24 September 2026

On pace for its date

Completion date (Land Department)
March 2028
Finish at recent pace
February 2028
Construction started
December 2024
Registered with the Land Department
September 2024
Community
Al Yelayiss 1
Units
770
Escrow bank
Emirates NBD
Name in Arabic
داماك صن سيتي
Land Department project number
3268
Land Department site inspections
6

Schedule

Since January 2026 Damac Sun City has added about 3.7 points a month. That puts 100% around February 2028, within three months of its registered completion date of March 2028.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

24 September 2026

37%+17 pts

  • Damac Sun City construction site, Land Department inspection photo 1, 24 September 2026
  • Damac Sun City construction site, Land Department inspection photo 2, 24 September 2026
  • Damac Sun City construction site, Land Department inspection photo 3, 24 September 2026
  • Damac Sun City construction site, Land Department inspection photo 4, 24 September 2026

20 May 2026

19%+12 pts

  • Damac Sun City construction site, Land Department inspection photo 1, 20 May 2026
  • Damac Sun City construction site, Land Department inspection photo 2, 20 May 2026
  • Damac Sun City construction site, Land Department inspection photo 3, 20 May 2026
  • Damac Sun City construction site, Land Department inspection photo 4, 20 May 2026

27 January 2026

7.1%+3.2 pts

  • Damac Sun City construction site, Land Department inspection photo 1, 27 January 2026
  • Damac Sun City construction site, Land Department inspection photo 2, 27 January 2026
  • Damac Sun City construction site, Land Department inspection photo 3, 27 January 2026
  • Damac Sun City construction site, Land Department inspection photo 4, 27 January 2026

20 August 2025

3.9%+2.0 pts

  • Damac Sun City construction site, Land Department inspection photo 1, 20 August 2025
  • Damac Sun City construction site, Land Department inspection photo 2, 20 August 2025
  • Damac Sun City construction site, Land Department inspection photo 3, 20 August 2025
  • Damac Sun City construction site, Land Department inspection photo 4, 20 August 2025

15 April 2025

1.9%+1.9 pts

  • Damac Sun City construction site, Land Department inspection photo 1, 15 April 2025
  • Damac Sun City construction site, Land Department inspection photo 2, 15 April 2025
  • Damac Sun City construction site, Land Department inspection photo 3, 15 April 2025
  • Damac Sun City construction site, Land Department inspection photo 4, 15 April 2025

29 August 2024

0%

  • Damac Sun City construction site, Land Department inspection photo 1, 29 August 2024
  • Damac Sun City construction site, Land Department inspection photo 2, 29 August 2024

All 41 site photos, by inspection date

Context

Al Yelayiss 1 has 18 projects under construction, 5.6% built on average.

Damac Elite Investment Co has 20 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Damac Sun City?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Damac Sun City be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac Sun City is built?
37%, measured at the Land Department site inspection on 24 September 2026. The Land Department engineers have inspected the site 6 times since August 2024.
Is Damac Sun City delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2028.
Who is building Damac Sun City?
The registered developer is Damac Elite Investment Co. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Sun City?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.