148 photos from 16 site inspections, newest first. The percentage is how much of Reem - Mira Oasis Community Phase 3 was built on the day of each visit.

19 January 2020100% built

22 December 201999% built

17 October 201994% built

11 July 201982% built

20 March 201978% built

21 October 201869% built

29 August 201866% built

6 May 201852% built

20 March 201843% built

22 November 201725% built

27 July 201714% built

29 March 201712% built

20 December 201610% built

24 August 20167.3% built

23 December 20157.3% built

2 June 20151.6% built

Back to Reem - Mira Oasis Community Phase 3 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.