Skip to content

Damac Islands - Maldives 2 construction progress

The registered completion date for Damac Islands - Maldives 2 in Al Yelayiss 1 is December 2028. At the last site inspection, in July 2026, it was 14% built. The developer is Damac Elite Investment Co.

14%

Built, at the site inspection of 16 July 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
October 2029
Construction started
March 2025
First registered
January 2025
Community
Al Yelayiss 1
Units
380
Escrow bank
Emirates NBD
Name in Arabic
داماك ايلاندز - مالديفز 2
Project number
3437
Site inspections
4

Schedule

Between March 2026 and July 2026 the site added about 2.2 points a month. At that rate it would finish around October 2029, more than three months after its registered date of December 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 July 2026

14%+8.9 pts

  • Damac Islands - Maldives 2 construction site, inspection photo 1, 16 July 2026
  • Damac Islands - Maldives 2 construction site, inspection photo 2, 16 July 2026
  • Damac Islands - Maldives 2 construction site, inspection photo 3, 16 July 2026
  • Damac Islands - Maldives 2 construction site, inspection photo 4, 16 July 2026

13 March 2026

5.2%+4.8 pts

  • Damac Islands - Maldives 2 construction site, inspection photo 1, 13 March 2026
  • Damac Islands - Maldives 2 construction site, inspection photo 2, 13 March 2026
  • Damac Islands - Maldives 2 construction site, inspection photo 3, 13 March 2026
  • Damac Islands - Maldives 2 construction site, inspection photo 4, 13 March 2026

26 June 2025

0.4%+0.4 pts

  • Damac Islands - Maldives 2 construction site, inspection photo 1, 26 June 2025
  • Damac Islands - Maldives 2 construction site, inspection photo 2, 26 June 2025
  • Damac Islands - Maldives 2 construction site, inspection photo 3, 26 June 2025
  • Damac Islands - Maldives 2 construction site, inspection photo 4, 26 June 2025

29 November 2024

0%

  • Damac Islands - Maldives 2 construction site, inspection photo 1, 29 November 2024
  • Damac Islands - Maldives 2 construction site, inspection photo 2, 29 November 2024

All 23 site photos, by inspection date

Context

Al Yelayiss 1 has 18 projects under construction, 6.5% built on average.

Damac Elite Investment Co has 20 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Damac Islands - Maldives 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Islands - Maldives 2 handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Islands - Maldives 2?
Damac Islands - Maldives 2 was 14% built at the site inspection on 16 July 2026. The site has been inspected 4 times since November 2024. The Land Department took 23 site photos at its inspections.
Is Damac Islands - Maldives 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Damac Islands - Maldives 2?
The registered developer is Damac Elite Investment Co. It has 19 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Islands - Maldives 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.