Damac Islands - Maldives 1 construction progress
The registered completion date for Damac Islands - Maldives 1 in Al Yelayiss 1 is December 2028. At the last site inspection, in October 2026, it was 6.6% built. The developer is Damac Elite Investment Co.
6.6%
Built, at the site inspection of 12 October 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- December 2038
- Construction started
- March 2025
- First registered
- January 2025
- Developer
- Damac Elite Investment Co
- Community
- Al Yelayiss 1
- Units
- 397
- Escrow bank
- Emirates NBD
- Name in Arabic
- داماك ايلاندز - مالديفز 1
- Project number
- 3388
- Site inspections
- 4
Schedule
Between May 2026 and October 2026 the site added about 0.6 points a month. At that rate it would finish around December 2038, more than three months after its registered date of December 2028.
Site inspections
12 October 2026
6.6%+3.4 pts
4 May 2026
3.2%+2.9 pts
26 June 2025
0.4%+0.4 pts
9 December 2024
0%
Context
Al Yelayiss 1 has 18 projects under construction, 6.5% built on average.
Damac Elite Investment Co has 20 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Damac Islands - Maldives 1?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Damac Islands - Maldives 1 handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Damac Islands - Maldives 1?
- Damac Islands - Maldives 1 was 6.6% built at the site inspection on 12 October 2026. The site has been inspected 4 times since December 2024. The Land Department took 19 site photos at its inspections.
- Is Damac Islands - Maldives 1 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Damac Islands - Maldives 1?
- The registered developer is Damac Elite Investment Co. It has 19 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Islands - Maldives 1?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Sun CityAlso by Damac Elite Investment Co. 37%, Due March 2028.
- Damac Islands - Maldives 2Also by Damac Elite Investment Co. 14%, Due December 2028.
- Damac Islands - Maldives 3Also by Damac Elite Investment Co. 12%, Due December 2028.
- Damac Islands - Bali 1Also by Damac Elite Investment Co. 7.0%, Due December 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)