Skip to content

Reem - Mira Oasis Community construction progress

The register lists Reem - Mira Oasis Community in Al Yelayiss 1 as complete, with a registered completion date of December 2017. Its last site inspection on record was in January 2019. The developer is Al Aryam Phase Two.

100%

Built, at the site inspection of 23 January 2019

Construction complete

Registered completion date
December 2017
Construction started
August 2014
First registered
February 2014
Developer
Al Aryam Phase Two
Community
Al Yelayiss 1
Units
484
Escrow bank
Noor Bank
Name in Arabic
ريم - ميرا أوسيس كوميونتي
Project number
1488
Site inspections
12

Schedule

The register lists Reem - Mira Oasis Community as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 January 2019

100%+1.2 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 23 January 2019
  • Reem - Mira Oasis Community construction site, inspection photo 2, 23 January 2019
  • Reem - Mira Oasis Community construction site, inspection photo 3, 23 January 2019
  • Reem - Mira Oasis Community construction site, inspection photo 4, 23 January 2019

29 October 2018

99%+0.7 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 29 October 2018
  • Reem - Mira Oasis Community construction site, inspection photo 2, 29 October 2018
  • Reem - Mira Oasis Community construction site, inspection photo 3, 29 October 2018
  • Reem - Mira Oasis Community construction site, inspection photo 4, 29 October 2018

9 October 2018

98%+2.9 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 9 October 2018
  • Reem - Mira Oasis Community construction site, inspection photo 2, 9 October 2018
  • Reem - Mira Oasis Community construction site, inspection photo 3, 9 October 2018
  • Reem - Mira Oasis Community construction site, inspection photo 4, 9 October 2018

28 June 2018

95%+9.0 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 28 June 2018
  • Reem - Mira Oasis Community construction site, inspection photo 2, 28 June 2018
  • Reem - Mira Oasis Community construction site, inspection photo 3, 28 June 2018
  • Reem - Mira Oasis Community construction site, inspection photo 4, 28 June 2018

19 March 2018

86%+0.1 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 19 March 2018
  • Reem - Mira Oasis Community construction site, inspection photo 2, 19 March 2018
  • Reem - Mira Oasis Community construction site, inspection photo 3, 19 March 2018
  • Reem - Mira Oasis Community construction site, inspection photo 4, 19 March 2018

6 March 2018

86%+23 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 6 March 2018
  • Reem - Mira Oasis Community construction site, inspection photo 2, 6 March 2018
  • Reem - Mira Oasis Community construction site, inspection photo 3, 6 March 2018
  • Reem - Mira Oasis Community construction site, inspection photo 4, 6 March 2018

12 November 2017

63%+13 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 12 November 2017
  • Reem - Mira Oasis Community construction site, inspection photo 2, 12 November 2017
  • Reem - Mira Oasis Community construction site, inspection photo 3, 12 November 2017
  • Reem - Mira Oasis Community construction site, inspection photo 4, 12 November 2017

27 July 2017

50%+18 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 27 July 2017
  • Reem - Mira Oasis Community construction site, inspection photo 2, 27 July 2017
  • Reem - Mira Oasis Community construction site, inspection photo 3, 27 July 2017
  • Reem - Mira Oasis Community construction site, inspection photo 4, 27 July 2017

29 March 2017

32%+26 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 29 March 2017
  • Reem - Mira Oasis Community construction site, inspection photo 2, 29 March 2017
  • Reem - Mira Oasis Community construction site, inspection photo 3, 29 March 2017
  • Reem - Mira Oasis Community construction site, inspection photo 4, 29 March 2017

23 December 2015

6.7%+3.4 pts

  • Reem - Mira Oasis Community construction site, inspection photo 1, 23 December 2015
  • Reem - Mira Oasis Community construction site, inspection photo 2, 23 December 2015
  • Reem - Mira Oasis Community construction site, inspection photo 3, 23 December 2015
  • Reem - Mira Oasis Community construction site, inspection photo 4, 23 December 2015

All 101 site photos, by inspection date

Context

Al Yelayiss 1 has 18 projects under construction, 6.5% built on average.

Own a unit in Reem - Mira Oasis Community?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Reem - Mira Oasis Community handover date?
Construction of Reem - Mira Oasis Community is recorded as complete, with a registered completion date of December 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Reem - Mira Oasis Community?
Reem - Mira Oasis Community was 100% built at the site inspection on 23 January 2019. The site has been inspected 12 times since January 2015. The Land Department took 101 site photos at its inspections.
Is Reem - Mira Oasis Community delayed?
The register lists construction as complete.
Who is building Reem - Mira Oasis Community?
The registered developer is Al Aryam Phase Two.
Which bank holds the escrow account for Reem - Mira Oasis Community?
Noor Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.