Reem - Mira Oasis Community construction photos

101 photos from 12 site inspections, newest first. The percentage is how much of Reem - Mira Oasis Community was built on the day of each visit.

23 January 2019100% built

29 October 201899% built

9 October 201898% built

28 June 201895% built

19 March 201886% built

6 March 201886% built

12 November 201763% built

27 July 201750% built

29 March 201732% built

23 December 20156.7% built

21 May 20153.3% built

22 January 201524% built

Back to Reem - Mira Oasis Community construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.