Skip to content

Damac Lagoons - Valencia construction progress

The registered completion date for Damac Lagoons - Valencia in Al Hebiah Fifth is February 2028. At the last site inspection, in May 2026, it was 5.2% built. The developer is Island Oasis Properties.

5.2%

Built, at the site inspection of 20 May 2026

Running behind its date

Registered completion date
February 2028
Finish at recent pace
November 2045
Construction started
November 2024
First registered
September 2024
Units
1,558
Escrow bank
First Abu Dhabi Bank
Name in Arabic
داماك لاجونز - فالينسيا
Project number
3226
Site inspections
3

Schedule

Between April 2025 and May 2026 the site added about 0.4 points a month. At that rate it would finish around November 2045, more than three months after its registered date of February 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 May 2026

5.2%+5.1 pts

  • Damac Lagoons - Valencia construction site, inspection photo 1, 20 May 2026
  • Damac Lagoons - Valencia construction site, inspection photo 2, 20 May 2026
  • Damac Lagoons - Valencia construction site, inspection photo 3, 20 May 2026
  • Damac Lagoons - Valencia construction site, inspection photo 4, 20 May 2026

29 April 2025

0.1%+0.1 pts

  • Damac Lagoons - Valencia construction site, inspection photo 1, 29 April 2025
  • Damac Lagoons - Valencia construction site, inspection photo 2, 29 April 2025

7 August 2024

0%

  • Damac Lagoons - Valencia construction site, inspection photo 1, 7 August 2024
  • Damac Lagoons - Valencia construction site, inspection photo 2, 7 August 2024

All 8 site photos, by inspection date

Context

Al Hebiah Fifth has 20 projects under construction, 49% built on average.

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Damac Lagoons - Valencia?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Lagoons - Valencia handover date?
The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2045. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Lagoons - Valencia?
Damac Lagoons - Valencia was 5.2% built at the site inspection on 20 May 2026. The site has been inspected 3 times since August 2024. The Land Department took 8 site photos at its inspections.
Is Damac Lagoons - Valencia delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Damac Lagoons - Valencia?
The registered developer is Island Oasis Properties. It has 25 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Valencia?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.