Skip to content

Damac Lagoons - Marbella construction progress

Damac Lagoons - Marbella in Al Hebiah Fifth is 87% built at the Land Department inspection of September 2026. Developer Island Oasis Properties. Completion registered for December 2025.

87%

Built, at the Land Department site inspection of 30 September 2026

9 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
March 2027
Construction started
February 2023
Registered with the Land Department
October 2022
Units
609
Escrow bank
Emirates NBD
Name in Arabic
داماك لاجونز- ماربيلا
Land Department project number
2489
Land Department site inspections
11

Schedule

Damac Lagoons - Marbella was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 2.4 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 September 2026

87%+2.8 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 30 September 2026
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 30 September 2026
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 3, 30 September 2026
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 4, 30 September 2026

17 August 2026

85%+9.8 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 17 August 2026
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 17 August 2026
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 3, 17 August 2026
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 4, 17 August 2026

21 April 2026

75%+12 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 21 April 2026
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 21 April 2026
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 3, 21 April 2026
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 4, 21 April 2026

21 November 2025

63%+9.2 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 21 November 2025
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 21 November 2025
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 3, 21 November 2025
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 4, 21 November 2025

24 June 2025

54%+11 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 24 June 2025
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 24 June 2025
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 3, 24 June 2025
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 4, 24 June 2025

18 February 2025

42%+12 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 18 February 2025
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 18 February 2025
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 3, 18 February 2025
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 4, 18 February 2025

26 September 2024

30%+21 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 26 September 2024
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 26 September 2024
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 3, 26 September 2024
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 4, 26 September 2024

18 April 2024

8.6%+8.1 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 18 April 2024
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 18 April 2024
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 3, 18 April 2024
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 4, 18 April 2024

21 August 2023

0.5%+0.2 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 21 August 2023
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 21 August 2023
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 3, 21 August 2023
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 4, 21 August 2023

4 May 2023

0.3%+0.3 pts

  • Damac Lagoons - Marbella construction site, Land Department inspection photo 1, 4 May 2023
  • Damac Lagoons - Marbella construction site, Land Department inspection photo 2, 4 May 2023

All 74 site photos, by inspection date

Context

Al Hebiah Fifth has 20 projects under construction, 48% built on average.

Island Oasis Properties has 27 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Damac Lagoons - Marbella?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Damac Lagoons - Marbella be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac Lagoons - Marbella is built?
87%, measured at the Land Department site inspection on 30 September 2026. The Land Department engineers have inspected the site 11 times since February 2023.
Is Damac Lagoons - Marbella delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Damac Lagoons - Marbella?
The registered developer is Island Oasis Properties. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Marbella?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.