Damac Lagoons - Lagoon Views 9 construction progress

The registered completion date for Damac Lagoons - Lagoon Views 9 in Al Hebiah Fifth is March 2027. At the last site inspection, in September 2026, it was 47% built. The developer is Island Oasis Properties.

47%

Built, at the site inspection of 1 September 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
May 2028
Construction started
August 2024
First registered
July 2024
Units
108
Escrow bank
First Abu Dhabi Bank
Name in Arabic
داماك لاجونز - لاجون فيوز 9
Project number
3116
Site inspections
6

Schedule

Between December 2025 and September 2026 the site added about 2.6 points a month. At that rate it would finish around May 2028, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 September 2026

47%+11 pts

  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 1, 1 September 2026
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 2, 1 September 2026
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 3, 1 September 2026
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 4, 1 September 2026

10 April 2026

37%+12 pts

  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 1, 10 April 2026
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 2, 10 April 2026
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 3, 10 April 2026
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 4, 10 April 2026

9 December 2025

25%+12 pts

  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 1, 9 December 2025
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 2, 9 December 2025
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 3, 9 December 2025
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 4, 9 December 2025

24 July 2025

13%+12 pts

  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 1, 24 July 2025
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 2, 24 July 2025
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 3, 24 July 2025
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 4, 24 July 2025

10 March 2025

1.0%+1.0 pts

  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 1, 10 March 2025
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 2, 10 March 2025
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 3, 10 March 2025
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 4, 10 March 2025

3 June 2024

0%

  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 1, 3 June 2024
  • Damac Lagoons - Lagoon Views 9 construction site, inspection photo 2, 3 June 2024

All 35 site photos, by inspection date

Context

Al Hebiah Fifth has 20 projects under construction, 49% built on average.

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Damac Lagoons - Lagoon Views 9?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Lagoons - Lagoon Views 9 handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Lagoons - Lagoon Views 9?
Damac Lagoons - Lagoon Views 9 was 47% built at the site inspection on 1 September 2026. The site has been inspected 6 times since June 2024. The Land Department took 35 site photos at its inspections.
Is Damac Lagoons - Lagoon Views 9 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Damac Lagoons - Lagoon Views 9?
The registered developer is Island Oasis Properties. It has 25 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Lagoon Views 9?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.