Damac Lagoons - Lagoon Views 6 construction progress

No completion date is registered for Damac Lagoons - Lagoon Views 6 in Al Hebiah Fifth yet. At the last site inspection, in August 2026, it was 42% built. The developer is Island Oasis Properties.

42%

Built, at the site inspection of 17 August 2026

Finish at recent pace
July 2028
Construction started
April 2024
First registered
April 2024
Units
48
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
داماك لاجونز - لاجون فيوز 6
Project number
2945
Site inspections
6

Schedule

Since December 2025 Damac Lagoons - Lagoon Views 6 has added about 2.5 points a month. At that rate the site reaches 100% around July 2028. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

17 August 2026

42%+5.0 pts

  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 1, 17 August 2026
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 2, 17 August 2026
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 3, 17 August 2026
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 4, 17 August 2026

10 April 2026

37%+16 pts

  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 1, 10 April 2026
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 2, 10 April 2026
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 3, 10 April 2026
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 4, 10 April 2026

8 December 2025

21%+8.3 pts

  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 1, 8 December 2025
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 2, 8 December 2025
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 3, 8 December 2025
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 4, 8 December 2025

14 August 2025

13%+11 pts

  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 1, 14 August 2025
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 2, 14 August 2025
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 3, 14 August 2025

18 April 2025

1.7%+1.7 pts

  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 1, 18 April 2025
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 2, 18 April 2025
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 3, 18 April 2025

12 February 2024

0%

  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 1, 12 February 2024
  • Damac Lagoons - Lagoon Views 6 construction site, inspection photo 2, 12 February 2024

All 28 site photos, by inspection date

Context

Al Hebiah Fifth has 20 projects under construction, 49% built on average.

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Damac Lagoons - Lagoon Views 6?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Lagoons - Lagoon Views 6 handover date?
No completion date is on record for Damac Lagoons - Lagoon Views 6 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Damac Lagoons - Lagoon Views 6?
Damac Lagoons - Lagoon Views 6 was 42% built at the site inspection on 17 August 2026. The site has been inspected 6 times since February 2024. The Land Department took 28 site photos at its inspections.
Who is building Damac Lagoons - Lagoon Views 6?
The registered developer is Island Oasis Properties. It has 25 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Lagoon Views 6?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.