Damac Lagoons - Lagoon Views 3 construction progress

No completion date is registered for Damac Lagoons - Lagoon Views 3 in Al Hebiah Fifth yet. At the last site inspection, in November 2026, it was 50% built. The developer is Island Oasis Properties.

50%

Built, at the site inspection of 5 November 2026

Finish at recent pace
August 2029
Construction started
April 2024
First registered
March 2024
Units
162
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
داماك لاجونز - لاجون فيوز 3
Project number
2942
Site inspections
7

Schedule

Since January 2026 Damac Lagoons - Lagoon Views 3 has added about 1.5 points a month. At that rate the site reaches 100% around August 2029. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

5 November 2026

50%+11 pts

  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 1, 5 November 2026
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 2, 5 November 2026
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 3, 5 November 2026
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 4, 5 November 2026

15 May 2026

39%+3.3 pts

  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 1, 15 May 2026
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 2, 15 May 2026
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 3, 15 May 2026
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 4, 15 May 2026

24 January 2026

36%+23 pts

  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 1, 24 January 2026
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 2, 24 January 2026
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 3, 24 January 2026
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 4, 24 January 2026

1 October 2025

13%+4.6 pts

  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 1, 1 October 2025
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 2, 1 October 2025
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 3, 1 October 2025
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 4, 1 October 2025

16 May 2025

8.0%+7.4 pts

  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 1, 16 May 2025
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 2, 16 May 2025
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 3, 16 May 2025
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 4, 16 May 2025

18 September 2024

0.6%+0.6 pts

  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 1, 18 September 2024
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 2, 18 September 2024
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 3, 18 September 2024

12 February 2024

0%

  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 1, 12 February 2024
  • Damac Lagoons - Lagoon Views 3 construction site, inspection photo 2, 12 February 2024

All 37 site photos, by inspection date

Context

Al Hebiah Fifth has 20 projects under construction, 49% built on average.

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Damac Lagoons - Lagoon Views 3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Lagoons - Lagoon Views 3 handover date?
No completion date is on record for Damac Lagoons - Lagoon Views 3 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Damac Lagoons - Lagoon Views 3?
Damac Lagoons - Lagoon Views 3 was 50% built at the site inspection on 5 November 2026. The site has been inspected 7 times since February 2024. The Land Department took 37 site photos at its inspections.
Who is building Damac Lagoons - Lagoon Views 3?
The registered developer is Island Oasis Properties. It has 25 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Lagoon Views 3?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.