Skip to content

Damac Lagoons - Lagoon Views 12 construction progress

The registered completion date for Damac Lagoons - Lagoon Views 12 in Al Hebiah Fifth is June 2027. At the last site inspection, in July 2026, it was 37% built. The developer is Island Oasis Properties.

37%

Built, at the site inspection of 17 July 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
December 2027
Construction started
November 2024
First registered
August 2024
Units
322
Escrow bank
First Abu Dhabi Bank
Name in Arabic
داماك لاجونز - لاجون فيوز 12
Project number
3214
Site inspections
5

Schedule

Between November 2025 and July 2026 the site added about 3.7 points a month. At that rate it would finish around December 2027, more than three months after its registered date of June 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 July 2026

37%+18 pts

  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 1, 17 July 2026
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 2, 17 July 2026
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 3, 17 July 2026
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 4, 17 July 2026

25 March 2026

19%+12 pts

  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 1, 25 March 2026
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 2, 25 March 2026
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 3, 25 March 2026
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 4, 25 March 2026

14 November 2025

6.7%+6.6 pts

  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 1, 14 November 2025
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 2, 14 November 2025
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 3, 14 November 2025
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 4, 14 November 2025

29 April 2025

0.1%+0.1 pts

  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 1, 29 April 2025
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 2, 29 April 2025
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 3, 29 April 2025

31 July 2024

0%

  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 1, 31 July 2024
  • Damac Lagoons - Lagoon Views 12 construction site, inspection photo 2, 31 July 2024

All 27 site photos, by inspection date

Context

Al Hebiah Fifth has 20 projects under construction, 49% built on average.

Island Oasis Properties has 26 projects under construction in Dubai; 7 have passed their registered completion date.

Own a unit in Damac Lagoons - Lagoon Views 12?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Lagoons - Lagoon Views 12 handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Lagoons - Lagoon Views 12?
Damac Lagoons - Lagoon Views 12 was 37% built at the site inspection on 17 July 2026. The site has been inspected 5 times since July 2024. The Land Department took 27 site photos at its inspections.
Is Damac Lagoons - Lagoon Views 12 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Damac Lagoons - Lagoon Views 12?
The registered developer is Island Oasis Properties. It has 25 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Lagoons - Lagoon Views 12?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.