Damac Lagoons - Lagoon Views 12 construction progress
Damac Lagoons - Lagoon Views 12 in Al Hebiah Fifth is 37% built at the Land Department inspection of July 2026. Developer Island Oasis Properties. Completion registered for June 2027.
37%
Built, at the Land Department site inspection of 17 July 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- December 2027
- Construction started
- November 2024
- Registered with the Land Department
- August 2024
- Developer
- Island Oasis Properties
- Community
- Al Hebiah Fifth
- Units
- 322
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- داماك لاجونز - لاجون فيوز 12
- Land Department project number
- 3214
- Land Department site inspections
- 5
Schedule
Between November 2025 and July 2026 the site added about 3.7 points a month. At that rate it would finish around December 2027, more than three months after the June 2027 date registered with the Land Department.
Site inspections
17 July 2026
37%+18 pts
25 March 2026
19%+12 pts
14 November 2025
6.7%+6.6 pts
29 April 2025
0.1%+0.1 pts
31 July 2024
0%
Context
Al Hebiah Fifth has 20 projects under construction, 48% built on average.
Island Oasis Properties has 27 projects under construction in Dubai; 6 have passed their registered completion date.
Own a unit in Damac Lagoons - Lagoon Views 12?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Damac Lagoons - Lagoon Views 12 be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Damac Lagoons - Lagoon Views 12 is built?
- 37%, measured at the Land Department site inspection on 17 July 2026. The Land Department engineers have inspected the site 5 times since July 2024.
- Is Damac Lagoons - Lagoon Views 12 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Damac Lagoons - Lagoon Views 12?
- The registered developer is Island Oasis Properties. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Damac Lagoons - Lagoon Views 12?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac Lagoons - Nice 1Also by Island Oasis Properties. 94%, Due July 2025, passed.
- Damac Lagoons - Nice 2Also by Island Oasis Properties. 84%.
- Damac Lagoons - PortofinoAlso by Island Oasis Properties. 97%, Due June 2025, passed.
- Damac Lagoons - Venice (1)Also by Island Oasis Properties. 74%, Due September 2025, passed.
- Paradise HillsNearby in Al Hebiah Fifth. 84%, Due December 2025, passed.
- Reportage HillsNearby in Al Hebiah Fifth. 0.4%, Due June 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

