256 Dubai off-plan projects are past their completion date.
The Land Department's construction register on 8 November 2026, read against our October snapshot nineteen days earlier. Most of the change is small. The age of the inspections behind each percentage turned out to matter more.
By the Mulki team ·
On 8 November 2026 the Land Department's Mashrooi register listed 1,561 projects under construction, holding 495,263 units. The median project was 14.7% built. Of the 1,394 with a registered completion date, 256 had passed it short of 100%, five more than on 20 October. Another 372 are due within a year, and 279 of those are less than half built.
1,561
projects under construction, with 495,263 units between them.
256
past their registered completion date: 18.4% of the 1,394 with one.
835
projects last inspected more than three months ago, out of 1,558.
279 of 372
due within twelve months are less than half built.
What moved since October
Nineteen days separate this snapshot from the October one, so nobody should expect the city to look different. The register lost ten projects net. Finished and cancelled projects leave the active list while new registrations join it, and a net figure cannot tell those two apart.
The clearer signal is at the bottom of the range. In October, 234 projects were recorded at 0%. Now 216 are. Two snapshots cannot say how many of those started building and how many left the register, but fewer projects at zero is part of why the median rose from 13.3% to 14.7%.
| Measure | 20 October | 8 November |
|---|---|---|
| Projects under construction | 1,571 | 1,561 |
| Units in those projects | 496,408 | 495,263 |
| Median project, share built | 13.3% | 14.7% |
| Average project, share built | 26.8% | 27.4% |
| Still at 0% | 234 | 216 |
| Past their registered completion date | 251 | 256 |
| As a share of projects with a date | 17.9% | 18.4% |
| Due within twelve months | 365 | 372 |
| Of those, less than half built | 272 | 279 |
Dubai Land Department Mashrooi register, read 20 October and 8 November 2026. Active projects only. Built share as recorded at each project's latest site inspection.
The late list grew by five, and that is a net figure. Projects whose dates passed during the nineteen days joined it, while any that reached 100%, left the register or had their date updated dropped off. We did not follow them one by one.
How old the percentages are
A completion percentage is only as fresh as the inspection behind it. Of the 1,558 projects with a recorded inspection, 723 had one in the three months to 8 November. The other 835 are showing a figure from more than three months back.
For a buyer, that changes how to read a project page. Seeing 40% next to an inspection from last week tells you something different from 40% next to one from the spring, when the site may well have moved on since. Our guide to checking an off-plan project's progress covers where the figure comes from and what to do when a payment request arrives ahead of it.
Projects past their completion date
We count a project as late when its registered completion date had passed by 8 November 2026 and its latest inspection was below 100%. 256 qualify, 18.4% of the projects that carry a date. The median one is seven months over. As a group they are 63.4% built on average, and 72 of them are still below half, three more than in October.
| How late | Projects |
|---|---|
| Under 6 months | 102 |
| 6 to 11 months | 93 |
| 12 to 23 months | 34 |
| Two years or more | 27 |
| All projects past their date | 256 |
Dubai Land Department Mashrooi register, read 8 November 2026. Months counted from the registered completion date to 8 November 2026.
What is due in the next year
372 projects are registered to finish within twelve months. 200 of them were below 30% at their latest inspection.
| Registered to complete | Projects | Less than half built |
|---|---|---|
| Next six months | 202 | 129 |
| Next twelve months | 372 | 279 |
Dubai Land Department Mashrooi register, read 8 November 2026. Built share as recorded at each project's latest site inspection.
Further out, the dates pile up in 2027 and 2028, with 411 and 380 projects respectively. The register also still holds 63 active projects carrying a 2025 completion date. Each has its own page in the off-plan tracker, with the inspection photos.
By community
Jumeirah Village Circle still has the most projects under construction, 118, and the most past their date, 44 of the 103 with one. It is also among the furthest along at 41.2% on average. By share, the worst of the ten is Jumeirah Garden City, where 13 of 27 projects are late. Business Bay went from 11 late projects to 12, and Dubai Land Residence Complex from 6 to 8. See Jumeirah Village Circle and Business Bay for the projects themselves.
| Community | Projects | Past their date | Average built | Units |
|---|---|---|---|---|
| Jumeirah Village Circle | 118 | 44 | 41.2% | 30,057 |
| Palm Deira | 94 | 12 | 22.9% | 10,344 |
| Dubai Land Residence Complex | 63 | 8 | 27.0% | 17,140 |
| Dubai World Central | 53 | 10 | 30.2% | 31,980 |
| Business Bay | 43 | 12 | 35.6% | 20,903 |
| Al Furjan | 39 | 9 | 32.9% | 4,552 |
| Dubai South Residential District | 39 | 10 | 43.7% | 4,198 |
| Jumeirah Village Triangle | 30 | 4 | 28.0% | 10,085 |
| Dubai Investment Park Second | 27 | 0 | 11.1% | 9,178 |
| Jumeirah Garden City | 27 | 13 | 31.7% | 2,919 |
Dubai Land Department Mashrooi register, read 8 November 2026. 317 projects have no community recorded and are left out of this table.
By developer
Among the ten largest developers, Binghatti Developers has the most projects past their date, 14 of the 36 with one, up from 13. Its pipeline also moved the most among the big ten, from 27.1% to 30.6% built on average. Emaar Development and Sobha still have nothing past its date, though nine of Sobha's 27 projects have no registered date to miss.
A late project here may already be working to a new date that the register has not caught up with, since RERA asks developers to update their completion dates as it reviews projects. The developer pages, such as Binghatti Developers and Azizi Developments, list every project with its date.
| Developer | Projects | Past their date | Average built | Units |
|---|---|---|---|---|
| Azizi Developments | 57 | 10 | 31.7% | 38,809 |
| Emaar Development | 52 | 0 | 18.2% | 18,508 |
| Binghatti Developers | 37 | 14 | 30.6% | 34,607 |
| Island Oasis Properties | 27 | 8 | 50.8% | 12,306 |
| Sobha | 27 | 0 | 35.1% | 31,038 |
| Danube Properties Development | 23 | 4 | 28.3% | 19,319 |
| Emaar Dubai South DWC | 23 | 0 | 20.9% | 5,716 |
| Nshama Properties | 22 | 0 | 23.8% | 4,236 |
| The Palm Jebel Ali Co | 22 | 0 | 15.6% | 2,054 |
| Damac Elite Investment Co | 20 | 0 | 5.9% | 9,930 |
Dubai Land Department Mashrooi register, read 8 November 2026. Developer names as registered, with legal suffixes removed.
How we counted
Every project the Mashrooi register listed as active on 8 November 2026, read through the off-plan tracker on this site, set against the same count on 20 October. The built percentage is the one from the project's latest Land Department site inspection. Projects without a registered completion date, 167 of them, are left out of the late and due counts. Unit counts are as registered.
Derived from the Dubai Land Department's Mashrooi project register, read 8 November 2026. Figures change as inspections are published and dates amended; the off-plan tracker has the current numbers. General information, not advice on any specific project.
Questions
How many off-plan projects are under construction in Dubai in November 2026?
How many Dubai off-plan projects are delayed?
How current is the completion percentage on the register?
Which Dubai community has the most delayed projects?
Where can I check a single project?
Related
- Checking an off-plan project's progressWhere the percentage comes from, and what to do when a payment request runs ahead of the site.
- Dubai off-plan projects by construction progressEvery project in the register, with its latest inspection and registered completion date.
- Taking handover of an off-plan unitThe completion notice, the 30-day window and what falls due.

Own an off-plan unit? Mulki follows every inspection until the keys arrive.