Crystal Tower construction progress

The registered completion date for Crystal Tower in Warsan First Development is December 2028. At the last site inspection, in July 2026, it was 0.3% built. The developer is V H S Real Estate Developments.

0.3%

Built, at the site inspection of 1 July 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
July 2233
Construction started
January 2026
First registered
December 2025
Developer
V H S Real Estate Developments
Units
110
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
برج كريستال
Project number
4118
Site inspections
2

Schedule

Between October 2025 and July 2026 the site added about 0.0 points a month. At that rate it would finish around July 2233, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 July 2026

0.3%+0.3 pts

  • Crystal Tower construction site, inspection photo 1, 1 July 2026
  • Crystal Tower construction site, inspection photo 2, 1 July 2026
  • Crystal Tower construction site, inspection photo 3, 1 July 2026

16 October 2025

0%

  • Crystal Tower construction site, inspection photo 1, 16 October 2025
  • Crystal Tower construction site, inspection photo 2, 16 October 2025

All 5 site photos, by inspection date

Context

Warsan First Development has 3 projects under construction, 2.6% built on average.

Own a unit in Crystal Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Crystal Tower handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2233. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Crystal Tower?
Crystal Tower was 0.3% built at the site inspection on 1 July 2026. The site has been inspected 2 times since October 2025. The Land Department took 5 site photos at its inspections.
Is Crystal Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Crystal Tower?
The registered developer is V H S Real Estate Developments.
Which bank holds the escrow account for Crystal Tower?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.